Operation Manual
6.0 Start up, shut down and Cleaning in Place
6.1 Pump Start Up Check List
Yes
No
1.
Has the pipework system been flushed
through to purge welding slag and/or
any other hard solids?
2.
Have all obstructions been removed
from the pipework or pump?
3.
Are the pump connections and
pipework joints tight and leak-free?
4.
Is there lubrication in the pump and
drive unit?
5.
Are the pipework valves open?
6.
Are all safety guards in place?
7.
Start then stop the pump to check that
the product is flowing in the correct
direction?
8.
Are the pump speed/pressure and
temperature settings below the pump
maximum limitations?
When all answers are 'yes', the pump
may be used.
If there are any pumping problems refer to the fault finding chart
STP125 Page 13