Power+ PREMIUM, Installation Guide, rel.
1.7
2.
I
NSTALLATION
2.1
Installation checklist
Complete the following checklist as you perform the installation, initialization, configuration, and testing
procedures. Refer to the appropriate sections (specified in the
Reference
column) for detailed information
about each checklist item.
When the checklist is complete, fax it, along with a connection diagram, to
Gamatronic at +972-2-582-8875.
Table 1: Installation checklist
Power+ model and configuration
Customer
Address
Site
Phone
Power+ Premium Model
[ ]
Up to 50 kVA
[ ]
Up to 100 kVA
[ ]
3-3 Config.
[ ]
Other (specify)
No. of modules _____
No. of redundant modules _____
Serial numbers:
System_________________ Static Switch ____________________
Modules 1___________ 2___________ 3___________ 4___________ 5___________
6___________ 7___________ 8___________ 9___________ 10___________
Technician Name
Date
Signature
√
Operation
Requirement
Reference
V i s u a l I n s p e c t i o n
Verify the physical integrity of the system
No physical damage
Verify that all components and modules are in
place
Components and modules are
securely fastened to shelves
2.3.1 Step 3
Comments on visual inspection: __________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
S i t e P r e p a r a t i o n – P h ys i c a l
Check ambient temperature
Recommended range:
+15 ~ +25 °C (+59 ~ +77 ° F)
Min/max:
–10 / +40 °C (+14 / +104 °F)
2.3.2 Step 1
Check humidity and condensation
No condensation/dampness
2.3.2 Step 2
Check ventilation
Proper airflow to batteries
2.3.2 Step 3
Check foundation and access
Adequate structure and access
2.3.2 Step 4
Check for adequate clearances
91 cm (36 in.) at rear and
100 cm (39 in.) at front
2.3.2 Step 5
Comments on site preparation
–
physical: __________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
S i t e P r e p a r a t i o n – E l e c t r i c a l
Check circuit breakers on electrical boards
supplying the Power+
Meet local code and Gamatronic
recommendations
2.3.3 Step 1
Check diameter of input and output power
cables connections, GND, and neutral lines
Meet local code and Gamatronic
recommendations
2.3.3 Step 2