12.0 

REMOVING AND INSPECTING MIXER CARTRIDGE 

 

 

1

. Remove handle assembly 

  Unscrew the tamper proof screw from handle. 

Pull out handle assembly from the body

 

2. Remove flange and faceplate  

  Unscrew the three screws and pull out the flange 

and faceplate from unit.  

Do not remove the 

outer faceplate.

 

 

 

3. Isolate the shower 

  It is recommended the shower is isolated at 

supply. 

  To isolate the shower loosen the isolators in an 

anti-clockwise direction until they are touching 
the circlips. This closes the shut off valves. 

  Open the valve and check if there is a flow. 

 

4. Remove cartridge nut and check cartridge 

  Unscrew cartridge and remove from body. Check 

the cartridge for wear and damage.  Replace if 
required (replacement cartridge available through 
your supplier). 

  Check and clean the body of all debris.

 

 

5. Re-assemble 

  Re-assemble, by reversing steps 4 to 1. 

  To re-open the shut off valves tighten the flow regulator/check valve/filter units until tightened (do not over 

tighten) and refit the two clips. 

  Check for leaks and correct operation. 

Note:

 Before tightening the flange make sure the handle fits correctly. Fit screws into flange and finger tighten. The flange should still 

be able to move. Slide the handle onto spline and move the flange until central to the handle. Remove handle and tighten the screws 
(it is best to tighten the screws in sequence a little at a time to avoid the flange moving). Refit handle.

 

 
 

 

Summary of Contents for CliniMix CP-BS

Page 1: ...s The GalvinCare paddle handle provides straight forward temperature control and minimises ligature risk Suitable for high and low pressure systems with a thermostatically controlled water temperature...

Page 2: ...e operation provided it is installed commissioned operated and maintained as per the recommendations outlined in this manual It should be noted however that this valve should not be considered as an a...

Page 3: ...cordance with the provisions of AS NZS 3500 Installations not complying with AS NZS 3500 may void the product and performance warranty provisions 7 0 INSTALLATION The CliniMix Thermostatic Progressive...

Page 4: ...s a split second it is still considered to be outside the operating conditions and may cause the valve to operate incorrectly In the event that this does occur measures must be taken to control the sp...

Page 5: ...Before tightening the flange make sure the handle fits correctly Put screws into flange and tighten finger tight the flange should still be able to move Slide the handle onto spline and move the flang...

Page 6: ...f the outlet temperature requires adjustment then follow the temperature adjustment in the installation instructions Shut Down Test Once the correct outlet temperature has been achieved the valves int...

Page 7: ...flow to stabilise for at least 15 seconds and record the temperature Quickly isolate the hot water supply to the valve The outlet flow should quickly reduce to be less than 0 4L min following the isol...

Page 8: ...a time to avoid the flange moving Refit handle 8 Fit the handle and fasten so the arrow shape on top of the handle matches the marking on the faceplate 11 0 ADJUSTMENT OF THE MIX TEMPERATURE 1 Set the...

Page 9: ...ove cartridge nut and check cartridge Unscrew cartridge and remove from body Check the cartridge for wear and damage Replace if required replacement cartridge available through your supplier Check and...

Page 10: ...mperature outlet then a 6 monthly servicing cycle may be adopted Otherwise servicing checks should be carried out more frequently e g every 4 months Follow the recommended maintenance procedures detai...

Page 11: ...aged Raise hot water temperature Clean the cartridge ensuring that all debris is removed Mix temperature unstable Flow rate below 2L min Thermostatic cartridge contains debris or is damaged Strainers...

Page 12: ...hat system must be in accordance with its m nuf turer s re mmend t n the C de nd re ev nt st tut ry nd t te r Terr t ry requ rements 4 The valve must be returned to Galvin Engineering together with a...

Page 13: ...Pressure ________kPa Cold Water Pressure _______kPa Make of Mixing Valve _______________________ Model No ________________________ Size _________ Valve Location Building ______________________________...

Page 14: ...k It is hereby certified that all the commissioning work has been carried out by the undersigned in accordance with the requirements of the Codes of Practice indicated prior Date of Valve Commissioned...

Page 15: ...f Warm Water C One Outlet in Use All Req d Outlets in Use One Outlet in Use All Req d Outlets in Use 1 2 3 4 5 6 7 8 9 10 11 Give details of brand and model designation Commensurate with the design fl...

Page 16: ..._______________________________Signature ______________________ Date _______________________ Maintenance Tests Yes Date of Previous Service ______________________________________________ Previous Serv...