LCW - LCR
Unpacking
The packing must be carefully removed to avoid the risk of damaging the unit. Different packing materials
are used: wood, cardboard, nylon etc.
It is recommended to keep them separately and deliver them to suitable waste disposal or recycling
facilities in order to minimise their environmental impact.
Siting
You should bear in mind the following aspects when choosing the best site for installing the unit and the
relative connections:
- size and origin of water pipes;
- location of power supply;
- accessibility for maintenance or repairs;
- solidity of the supporting surface;
All models belonging to the LCW series are designed and built for indoor installation As special care has
been taken in the sound insulation and sealing of the components and hot parts in general, they need not
be installed in dedicated rooms.
It is advisable to place a rigid rubber strip between the base frame and the supporting surface.
INSTALLATION
Installation clearance requirements
In the case of units with a remote condenser, the plumbing and cooling connections are provided on the
top of the unit. This allows the chiller to be placed practically against the rear wall. It is nonetheless of
fundamental importance to assure the following service spaces:
-
back side min. 0 metres
-
electric control board side: min. 1.0 metre to guarantee access for inspection and/or
maintenance of cooling components
-
lateral part min. 0.5 metre for extraordinary maintenance
-
top side: min. 1.0 metre for adequate connection to the external hydraulic and cooling piping.