5 INSTALLATION
5.1
INSTALLATION CLEARANCE REQUIREMENTS
It is of fundamental importance to ensure an adequate volume of air both on the intake and outlet sides
of the finned condenser/evaporator coils; it is highly important to prevent the air delivered from being re-
aspirated as this may impair the performance of the unit or even cause an interruption in normal
operation. For this reason it is necessary to guarantee the following clearances (see figure on this page):
- rear side/plumbing connections: min. 1.0 metre to guarantee access to plumbing connections and/or for
any necessary maintenance on the pumps, reservoir, expansion tank and flow switch.
- electric control board side: min. 1.0 metre to guarantee access for inspection and/or maintenance of
cooling components
- finned pack heat exchanger side: min. 1.5 metres to ensure proper air circulation and access to the
compressor compartment, also from the side.
- top side: there must be no obstacle to expulsion.
Top view of the unit
1.0 m
rear
1.0 m
front
1.5 m
1.5 m