1 Pre-work preparations
7
E
1
Pre-work preparations
1
Complete the server information sheet in Appendix A.
2
Shutdown the server system if its running.
3
Turn off the server’s power (and any attached peripherals).
4
Disconnect all peripherals and unplug all device power cords.
2
Removing the hard disk units
After removing the front door, remove all the hard disk units from their 3.5-inch storage bays.
Note that these hard disks must be re-installed after the rack conversion is complete.
This section describes how to remove the hard disk units from their bays.
Notes:
Note that when converting the server from a deskside to a rackmount, the bay orientation is
different.
Make sure to write down the bay numbers and SCSI IDs for each hard disk so they can be
replaced to their proper locations.
Before moving the server, remove all hard disk units. Striking or
hitting a hard disk unit can corrupt its data.
Summary of Contents for PRIMERGY PG-R1CK6
Page 7: ...vi ...
Page 9: ...viii ...
Page 11: ...x ...
Page 13: ...2 本製品の梱包物 ブラケット C 1 2 M3 ネジ 6 M4 バインドネジ 4 M4 タップタイトネジ 4 M5 ネジ 1 8 M6 ネジ 1 4 部品 名称 数量 確認 ...
Page 15: ...4 本製品の梱包物 ...
Page 43: ...32 付録 ...
Page 49: ...vi ...
Page 51: ...viii ...
Page 55: ...4 Ensuring the package ...
Page 83: ...32 Conversion procedure ...
Page 85: ...34 ...