Maintenance Section 5-7
MAINTENANCE
FB42 08/01
© 2004
Alamo Group Inc.
MAINTENANCE
STORAGE
Your rotary cutter represents an investment from which you should get the greatest possible benefit. Therefore,
when the season is over, the cutter should be thoroughly checked and prepared for storage so that a minimum
amount of work will be required to put it back into operation for the next season. The following are suggested
storage procedures:
1. Thoroughly clean the cutter.
2. Lubricate the cutter as covered in Maintenance Section.
3. Tighten all bolts and pins to the recommended torque.
4. Check the cutter for worn or damaged parts. Make replacements immediately.
5. Store the cutter in a clean, dry place with the cutter housing resting on blocks.
6. Use spray touch-up enamel where necessary to prevent rust and maintain the appearance of the cutter.
PROPER TORQUE FOR FASTENERS
The torque chart
(Figure 7)
lists the correct tightening torque for fasteners. When bolts are to be tightened or
replaced, refer to this chart to determine the grade of bolts and the proper torque except when specific torque
values are assigned in manual text.
RECOMMENDED TORQUE IN FOOT POUNDS (NEWTON-METERS) UNLESS OTHERWISE STATED IN
THE MANUAL
NOTE:
These values apply to fasteners as received from supplier, dry or when lubricated with normal engine oil.
They do not apply if special graphited or molydisulphide greases or other extreme pressure lubricants are used.
This applies to both UNF fine and UNC coarse threads.
FIGURE 7.
Torque Chart
RECOMMENDED TORQUE IN FT-LBS (Nm)
COARSE AND FINE THREADS
Bolt
Plain
Three
Six
Diameter
Head
Dashes
Dashes
1/4
Not used
10 (14)
14 (19)
5/16
Not used
20 (27)
30 (41)
3/8
Not used
35 (47)
50 (68)
7/16
35 (47)
55 (75)
80 (108)
1/2
55 (75)
85 (115)
120 (163)
9/16
75 (102)
130 (176)
175 (237)
5/8
105 (142)
170 (230)
240 (325)
3/4
185 (251)
300 (407)
425 (576)
7/8
160 (217)
445 (603)
685 (929)
1
250 (339)
670 (908)
1030 (1396)
1-1/8
330 (447)
910 (1234)
1460 (1979)
1-1/4
480 (651)
1250 (1695)
2060 (2793)
2 (B)
5 (D)
8 (F)
Summary of Contents for FB42
Page 4: ......
Page 5: ...SAFETY SECTION Safety Section 1 1...
Page 19: ...INTRODUCTION SECTION Introduction Section 2 1...
Page 23: ...ASSEMBLY SECTION Assembly Section 3 1...
Page 27: ...OPERATION SECTION Operation Section 4 1 2001 Alamo Group Inc...
Page 62: ...OPERATION Operation Section 4 36 OPERATION 2004 Alamo Group Inc FB42 08 01...
Page 63: ...MAINTENANCE SECTION Maintenance Section 5 1...
Page 76: ...P N 00768114C FB42 SOM 08 01 Printed U S A...
Page 79: ......