4.7 Finishing configuration
Setting customer-specific parameters
❒ Set the parameters for heating times, storage tank loading times and DHW tank loading times
❒ Set the operating mode, times and temperatures for any standby boilers that may be connected
Performing the functional inspection
❒ Check that all drives and servo-motors are working properly and rotating in the direction indicated on the
circuit diagram
❒ Check that the contact switches on doors and ash containers as well as all safety equipment are working
properly
Before heating up for the first time
❒ Check the system pressure of the heating system
❒ Check that the heating system is fully ventilated
❒ Check that the safety devices are present and working correctly
❒ Check that there is sufficient ventilation in the boiler room
❒ Check the seal of the boiler
➥ All doors and inspection openings must be tightly sealed
4.8 Before commissioning / configuring the boiler
The boiler must be configured to the heating system during initial start-up!
NOTICE
Optimum efficiency and efficient, low-emission operation can only be guaranteed if the system
is set up by trained professionals and the standard factory settings are observed.
Take the following precautions:
❒ Initial startup should be carried out with an authorised installer or with Froling customer
services
NOTICE
Foreign bodies in the heating system impair its operational safety and can result in damage to
property.
As a result:
❒ The whole system should be rinsed out before initial start-up in accordance with EN 14336.
❒ Recommendation: Make sure the hose diameter of the flush nozzles in the flow and return
complies with ÖNORM H 5195 and is the same as the hose diameter in the heating
system, however not more than DN 50.
❒ Turn on the main switch
❒ Set the boiler controller to the system type.
❒ Load the boiler default values.
❒ Check the system pressure of the heating system
Initial startup
4
Finishing configuration
Service manual SPS 4000 | B0960622_en
27