INSTALLATION
Electrical Wiring for 265 Volt Models
14
PXCJA conduit kit (or equivalent) be installed on all hardwire
units. If installing a flush-floor mounted unit, make sure the
chassis can be removed from the sleeve for service and
maintenance.
WARNING
Electrical Shock Hazard
Turn off electrical power before service
or installation.
ALL electrical connections and wiring
MUST
be installed by a qualified
electrician and conform to the National
Code and all local codes which have
jurisdiction.
Failure to do so can result in property
damage, personal injury and/or death.
Electrical Wiring for 265 Volt
Models
Power Cord Installation
All 265V PTAC/PTHP units come with a factory installed non-LCDI
power cord for use in a subbase. If the unit is to be hard-wired refer to the
instruction
s in the installation section of this manual.
NOTE:
It is recommended that the PXSB subbase assembly, the
To install the line voltage power leads and con-
duit to chassis, follow the instructions below
and refer to Figures 25-27 on page 19. PXCJA
Conduit Kit is required with this setup.
1.
Follow the removal process of the chassis’s junction box
(Figure 25
in the Installation section
).
2.
Prepare the 265V (or 230V) power cord for connection to the chas-
sis’ power cord connector by cutting the cord to the appropriate
length (refer to Figure 26 and follow Figure 15). Power cord harness
selection shown on Table 2