6 Installation
00981795R03 – FZR20/25 LB, PL
Fill product simulation bottle
Fig. 4
1. Remove probe and cap from the top bottle and fill with solution used at
your facility (e.g., 60% glycerine and 40% water) (Fig. 4). Replace cap
and reinsert probe sensor.
2. If equipped with a bottom probe, perform same procedure for bottom
bottle.
ATTENTION INSTALLER
It is imperative that the top probe bottle be filled with a solution that your
facility uses to ensure proper operation of unit.
Fig. 5
3. Press lower left corner of front facade door to access power switch
inside (Fig. 5.1).
Fig. 6
4. Press power switch to turn unit on (Fig. 6.1).
5. Install (2) 9 V back-up interface batteries (Fig. 6.2) and (1) 9 V chart
recorder back-up battery (if equipped.)
1
1
2