Packing List
LP (Propane) Conversion Kit - Burner Orifices (2)-(#54), Pilot Orifice (0.14 LP), LP Regulator
Thimble (2-Piece Assembly)
Pipe Shield, Header Shield (shipped attached to top of fireplace)
Wall Switch, Cover Plate, and Wire (GSB2 and MV Only)
GreenSmart Remote Control (GSR2 Only)
Additional Items Required
Gas Line Equipment (shutoff valve, pipe, etc.)
Electrical Equipment (min. 14 gauge, grounded line)
This Fireplace Requires 8 lbs. (3.6 Kg) of 1/4” Crushed Glass
94500580 Platinum (10 lbs./4.55Kg)
94500581 Bronze (10 lbs./4.55Kg)
94500582 Cobalt (10 lbs./4.55Kg)
94500583 Black (10 lbs./4.55Kg)
Recommended Installation Procedure
Frame the opening for the fireplace. Make sure to allow for vent installation.
Install the vent, gas line and electrical hook-up.
Install the drywall.
Install the hearth (if applicable).
Install the facing (if applicable).
Install the mantel (if applicable).
Install fireback (optional).
Install logs (optional) and glass media.
Finalize the installation (see page 42).