Setup 

 

1.  Power up the panel. 

 

2.  The panel will automatically see the expansion card when it powers up and the additional zones 5 to 8 will 

be active (switched on).  If there are no devices connected to new zones 5 to 8 then four EOL faults will be 
generated. 
 

3.  It will be necessary to switch off any unused zones to prevent EOL faults. For example if only six zones are 

going to be used the two un-used zones will need to be switched off otherwise the panel will always be in 
fault. 
 

4.  Switching off un-used zones is done as follows: 

 
 
(a)  Log in to engineer level and selecting 

“zones” (option 6) in the main menu. 

(b)  Set the write enable switch to on. 
(c)  While still within the zones menu, select 

“zone status” (option 1) 

(d)  You will then have to enter the zone number to be switched off and then press enter. 
(e)  You will now be able to toggle the on/off status of the selected zone.  
 
Repeat steps (c) to (e) above for the next zone. 

 

(f)  Remember to set the write enable switch back to off when finished. 

 

 

 
 

 
Technical Data 

 

For  specifications  of  the  TWINFLEX

®

pro  Panel  when  upgraded  to  8  Zones,  please  see  the  TWINFLEX

®

pro 

Engineering & Commissioning Manual. 
 
 

 
 
 
 
 
 
 
 
 
 
 

Technical Support 

 

Contact your supplier for technical support on this product. 

Due  to  the  complexity  and  inherent  importance  of  a  life  risk  type  system,  training  on  this  equipment  is  essential,  and 
commissioning  should  only  be  carried  out  by  competent  persons.  Fike  cannot  guarantee  the  operation  of  any  equipment 
unless all documented instructions are complied with, without variation.  This unit complies with the EMC directive. 
 
Fike’s policy is one of continual improvement and the right to change a specification at any time without notice is reserved. 
Whilst every care has been taken to ensure that the contents of this document are correct at time of publication, Fike shall be 
under no liability whatsoever in respect of such contents. E&OE. 
 
TWINFLEX, Fike and Fike Corporation are registered trademarks of Fike Corporation and its subsidiaries. All other 
trademarks, trade names or company names referenced herein are the property of their respective owners.

 

Summary of Contents for Twinflex pro 505-0006

Page 1: ...g one of the push on battery leads at the battery Always disconnect the battery first before removing the mains power to the panel NOTE Do not disconnect the battery by removing the wires from the terminals on the CIE circuit board Doing this may allow the batteries to short circuit 3 Remove mains power from the panel by removing the fuse in the fused spur that supplies the panel or switching off ...

Page 2: ... will only fit one way 8 Flip the left hand CIE assembly back over anti clockwise and plug the other end of the ribbon cable assembly into the connector marked expansion connector on the CIE PCB again this will only fit one way 9 Slide the CIE assembly onto the base moulding ensure that the CIE assembly moulding engages into the clips on the base moulding and that all cables ends are accessible fo...

Page 3: ...directly to the Expansion Card For details of how to connect the zone cables see the TWINFLEX pro Engineering Commissioning Manual 12 Re connect the mains power to the panel before connecting the battery by refitting the fuse in the fused spur that supplies the panel or switching on the circuit breaker 13 Now re connect the battery 14 Refit the right hand cover moulding ensure the moulding engages...

Page 4: ...te enable switch back to off when finished Technical Data For specifications of the TWINFLEX pro Panel when upgraded to 8 Zones please see the TWINFLEX pro Engineering Commissioning Manual Technical Support Contact your supplier for technical support on this product Due to the complexity and inherent importance of a life risk type system training on this equipment is essential and commissioning sh...

Reviews: