SYSTEM CONTROL CHECK OUT PROCEDURES 

1.  Adjust the thermostat to call for heat and observe the power venting system for proper operation sequence  

(Repeat if necessary). 

a.  Thermostat calls for heat. 
b.  Relay is energized and venter motor starts. 
c.  Pressure switch closes and burner  starts. 
d.  Thermostat is satisfied, the burner stops. 
e.  This starts the post purge cycle. 

2.  While system is operating disconnect  power to the venter motor. This should open the pressure switch 

contacts and  stop burner operation. 

TROUBLE SHOOTING HINTS 

1.  Main burner does not fire when thermostat calls for heat with venter  operating. 

a.  Check pressure switch adjustment. 
b.  Check wiring connections between pressure switch and burner. c. Check pressure switch for conti-nuity 

across terminals, during venter operation. 

2.  Venter does not activate when thermostat calls for heat. 

a.  Check wiring. 
b.  Check relay for proper operation. 

3.  Flue gas odor. 

a.  Check system draft. 
b.  Check for negative pressure in building. 
c.  Check post purge time. 

MAINTENANCE 

1. 

Motor:

 Inspect motor once a year, the motor should rotate freely. 

2. 

Wheel:

 Inspect venter wheel annually to  clear any soot, ash or coating which inhibits either rotation or  air 

flow. Remove all foreign  material before operating. 

3. 

Vent System:

  Inspect all vent pipe connections annually for looseness and for evidence of flue gas 

leakage. Seal or tighten  pipe connections if necessary.

 

 

Summary of Contents for 46190700

Page 1: ...Kits can also control the operation of Field Draft Inducers and Combustion Air Systems ITEMS INCLUDED IN KIT 1 Junction box with mounted pressure switch and relay timer 1 1 Ft Length of 1 4 inch alumi...

Page 2: ...the CK 43 junction box or installer supplied junction box onto the wall or floor joist without straining the flexible conduit Fasten the CK 43 junction box through the four dimpled locations on the ba...

Page 3: ...at the front corners of the collar Bend 90 degrees 1 4 inch behind the single hole on the straps 2 Insert clamping screw in ears on collar and bolt the remainder of the collar together 3 Hold the coll...

Page 4: ...8 DO NOT move the weight attached directly to the gate this is used only for balancing at the factory ADJUSTING THE DRAFT CONTROL WITH 5 AF Vertical Flues Mounting The control is shipped for installa...

Page 5: ...to decrease post purge time To increase the operation time rotate the timer adjustment screw clockwise See Figure 11 Typical post purge time should be between 1 and 2 minutes WIRING CAUTION Disconnec...

Page 6: ...ter operating a Check pressure switch adjustment b Check wiring connections between pressure switch and burner c Check pressure switch for conti nuity across terminals during venter operation 2 Venter...

Page 7: ...INSTALLER S NAME _____________________________________________________ INSTALLER S COMPANY __________________________________________________ INSTALLER S PHONE NO ____________________________________...

Page 8: ...Page 8 P N 46190700 Rev C 09 01...

Reviews: