D

RAFT 

C

ONTROL 

I

NSTALLATION IN 

T

YPE 

B V

ENT 

P

IPE

 

CAUTION:

 

DO NOT use the supplied collar when mounting draft 

control to Type B Vent Pipe. Install by using a Type B Vent Pipe Tee.

 

1.  Install a vent pipe reducer or increaser into the inner pipe and  

fasten using sheet metal screws. (See  Figures 6 & 7) 

2.  The opening of the Type B Vent Tee, at the draft control mounting 

location,  should be sealed with a high temper-  ature sealant or 
equivalent. 

3.  Refer to Insertion of Draft Control Section. 

I

NSERTION OF 

D

RAFT 

C

ONTROL 

S

ECTION

 

Insert the draft control into the collar or tee. The front face of the 
control MUST be plumb and the bearing surfaces MUST be level 
whether the control is on a horizontal, vertical or sloping flue pipe. 
Use a spirit level and level accurately. (See Figures 6 & 7) Secure 
the control in the collar by tightening the clamping screws. If a tee is 
used or a collar is supplied locally, the control may be held in place 
by sheet metal screws. 

ADJUSTMENTS 

A

DJUSTING THE 

D

RAFT 

C

ONTROL WITH 

4" MG1 

The control MUST be adjusted to the desired draft setting by adding 
or removing the washer-type weights supported by the two chains on 
the side of the draft control. (See Figure 8) DO NOT move the weight 
attached directly to the gate, this is used only for balancing at the 
factory. 

A

DJUSTING THE 

D

RAFT 

C

ONTROL WITH 

5" AF 

Vertical Flues Mounting - 

The control is shipped for installation in a 

vertical flue. The adjustment weight should be in the right hand slot 
when you face the control. See Figure 9. 

Horizontal Flues Mounting  -

 For hori-zontal flues, remove the 

weight from the right hand slot and attach it to the left hand slot as 
shown in Figure 9. 

What Draft Setting to Use - 

When adjusting the control, two things 

are essential: 

1.  The burner must be operating for at least 10 minutes to obtain 

maximum chimney draft. 

2.  An analysis of the flue gases is  necessary to determine the 

percentage  of CO

2

 and check for presence of CO.  Refer to the appliance instructions and/or to the local 

gas company for the proper CO

2

 readings and allowable CO  levels. A rule of thumb for draft  setting is 

between .01" to .03" of water column draft at the appliance outlet. (Check equipment requirement.)  

Changes in the adjustment of the 4" MG1 control should be made by adding or removing the washer-like 
weights (supplied with the control) to or from the weight holder chain assembly. After the control is adjusted, 
it's action will be entirely automatic, the gate will open or close by itself to correct for changes in the draft that 
occur in the chimney. 

Figure 7

Figure 6

Figure 8

Figure 9

Summary of Contents for 46190700

Page 1: ...Kits can also control the operation of Field Draft Inducers and Combustion Air Systems ITEMS INCLUDED IN KIT 1 Junction box with mounted pressure switch and relay timer 1 1 Ft Length of 1 4 inch alumi...

Page 2: ...the CK 43 junction box or installer supplied junction box onto the wall or floor joist without straining the flexible conduit Fasten the CK 43 junction box through the four dimpled locations on the ba...

Page 3: ...at the front corners of the collar Bend 90 degrees 1 4 inch behind the single hole on the straps 2 Insert clamping screw in ears on collar and bolt the remainder of the collar together 3 Hold the coll...

Page 4: ...8 DO NOT move the weight attached directly to the gate this is used only for balancing at the factory ADJUSTING THE DRAFT CONTROL WITH 5 AF Vertical Flues Mounting The control is shipped for installa...

Page 5: ...to decrease post purge time To increase the operation time rotate the timer adjustment screw clockwise See Figure 11 Typical post purge time should be between 1 and 2 minutes WIRING CAUTION Disconnec...

Page 6: ...ter operating a Check pressure switch adjustment b Check wiring connections between pressure switch and burner c Check pressure switch for conti nuity across terminals during venter operation 2 Venter...

Page 7: ...INSTALLER S NAME _____________________________________________________ INSTALLER S COMPANY __________________________________________________ INSTALLER S PHONE NO ____________________________________...

Page 8: ...Page 8 P N 46190700 Rev C 09 01...

Reviews: