CONNECTING THE BOILER
5.1 Place the boiler on its back.
5.2 Remove the boiler base plate, four screws (fig. 16). Remove the plugs fitted to the boiler water connections.
Remove the bag of sealing washers from the boiler pipework. Remove the front panel by gripping on
both sides, sliding up and pulling away from the main boiler.
5.3 Lift boiler as shown in fig. 15 onto the fixing bolts and fit supplied nuts and washers.
5.4 Connect installation pipe work to boiler valves in the order shown in fig. 11.
5.5 Connect the pressure relief valve discharge pipe (15 mm) to the outside of the building, where possible over
a drain. The discharge must be such that it will not be hazardous to occupants or passers-by cause damage
to external electric components or wiring. The pipe should be directed towards the wall.
It must not discharge above an entrance or window, or any type of public access. The installer must consider that
the overflow could discharge boiling water.
TOP VIEW BOILER SIDE OUTLET
Fig. 14
Fixing screws
Front
Key slot holes
Fixing screws
rear
Fig. 16
Fixing points
Fig. 15
Lift here