3.2 INSTALLATION AND ADJUSTMENT PROCEDURE OF THE BREAK-OUT MOBILE LEAF 

 

Step 

Ref.  Description 

Cut the sliding guide (H) to measure Lm (or higher), and attach it to the floor, as shown in the drawings of the 
various types of door available in this manual, with screws not supplied by us. 

Fix the leaf to the automation carriages, using at least 2 fixing screws, and add the second upper wheel (K) on 
each carriage. 

Adjust the pressure of the lower pin (C) on the sliding guide (H), as shown in fig. 2. 

B1 

To level any collapse of the break-out leaf, proceed as shown in fig. 2 and as indicated below: 

- Loosen the B2 and B3 screws, 

- Tighten the B1 screw until you get the levelling of leaf, 

- Tighten the B2 and B3 screws. 

Adjust the force necessary for the break-out of the leaf, as shown in fig. 2. 

- To increase/reduce the manual force to break-out leaf, tighten/loosen the screw on the side of the coupling 
pin (F); 

- if you want to further reduce the manual force to break out leaf, you can increase the measurement of 150 
mm to fixing the coupling pin (E) and (F). 

Note: verify that the force required to break-out every door does not exceed the value of 220N, as required 
by the EN 16005 European standard. 

Fix  the  PH3  photocell  on  wall  at  the  top,  through  the  KPH1E  support,  so  that  the  break-out  of  the  leaf  is 
detected by the photocell, as indicated in Figure 6. 

Make the electrical connections of the PH3 photocell to the electronic control 5CB01, as shown in Figure 3. 

Apply on the leaf, in a visible location and in the direction of the break-out, the label supplied indicating the 
emergency exit, as illustrated in Figure 2. 

 

FIGURE 2: KBS1E adjustments 

   

 

 

     

  

 

 

 

 

 

 

 

 

 

 

 

 

Summary of Contents for KBS1E

Page 1: ...R SLIDING DOOR ASSEMBLED MANUAL KBS1E SLIDING DOORS BREAK OUT SYSTEM KBS1D SIDE WALLS BREAK OUT SYSTEM D112 All technical and commercial documents are available in the DOWNLOAD area of the website www...

Page 2: ...em must comply with the European standard EN 16005 and are CE marked in accordance with the Machinery Directive 2006 42 EC Break out systems of the KBS1E sliding doors and KBS1D side walls in conjunct...

Page 3: ...mm Minimum width Lm 600 mm Maximum weight 120 kg x 0 8 m 100 kg Sliding doors fixing to the carriages Use at least 2 screws per carriage see ref A in the figure Upper wheels on automation carriages Ad...

Page 4: ...rews not supplied by us Note in case of doors with 2 leaves it s preferable to cut the profile few millimetres longer Lm 2 to cover the gap which is determined in the upper part of the doors closed po...

Page 5: ...D112 EN 2021 05 01 5 www facespa it FIGURE 1 KBS1E assembly drawing...

Page 6: ...screws 5 F Adjust the force necessary for the break out of the leaf as shown in fig 2 To increase reduce the manual force to break out leaf tighten loosen the screw on the side of the coupling pin F i...

Page 7: ...able supplied to the terminals of electronic control as follow blue wire terminal 0 brown wire terminal 1 black wire do not connect Connect the receiver using the grey cable supplied to the terminals...

Page 8: ...D112 EN 2021 05 01 8 www facespa it FIGURE 6 KBS1E horizontal sizes...

Page 9: ...D112 EN 2021 05 01 9 www facespa it FIGURE 7 KBS1D horizontal sizes...

Page 10: ...aluminium between the sliding leaf and the side wall when the sliding leaves and side walls are break out 6 D If necessary fix the hook brackets D to the side wall using the provided screws respect t...

Page 11: ...D112 EN 2021 05 01 11 www facespa it FIGURE 8 KBS1D assembly drawing...

Page 12: ...D112 EN 2021 05 01 12 www facespa it FIGURA 9 KBS1D adjustments FACE S r l Viale delle Industrie 74 31030 Dosson di Casier Treviso Italy www facespa it...

Reviews: