![EZ Way Comfortline II Operator Instructions Manual Download Page 10](http://html1.mh-extra.com/html/ez-way/comfortline-ii/comfortline-ii_operator-instructions-manual_2457966010.webp)
10
Installation Instructions
The HiLo Bathtub Comfortline II is delivered to you fully assembled, ready to be connected to the water and
power supply at the customer’s premises and should be installed according to local guidelines and regulations.
Assembly Process
DO NOT DRAG NOR PUSH THE BATHTUB ACROSS THE FLOOR AS THIS COULD CAUSE
DAMAGE TO THE LEGS OR ACTUATORS.
When lifted, do so briefly and use at least two persons.
1.
Once the bathtub is in its final position, lift briefly at each end again to release any tensions that might have
been created between the feet during installation.
2.
The adjustable feet are used to level/adjust the bathtub. Please bear in mind that the head end of the bathtub
has to be approximately 2 cm / 3/4” higher than the foot end to allow the water to drain more easily.
3.
Please flush the pipework before connecting the Comfortline to protect the bathtub fittings from dirt.
4.
A CERTFIED ELECTRICIAN SHALL CONNECT THE MAINS CORD TO A WALL-MOUNTED
OUTLET (SPLASHPROOF) in accordance with local regulations.
5.
Use the flexible drain hose to establish a connection between the drain siphon (at the bottom of the tub)
and the floor gully. This connection is best attached when the bathtub is raised into its highest position.
6.
Carry out functional test.
•
Test the Up/Down function by pushing each button on the hand control. INITIALIZIATION must be carried
out if the tub does not raise evenly (see separate instruction in the manual).
•
Check that the thermostat is working properly and test the water temperature. If the temperature is not the
same as the actual water temperature, adjust according to manufacturer’s instructions (see separate thermostatic
mixer operating manual).
•
Check that the bath tap and the shower work properly.
•
Check the cold/hot water connections and make sure the drain hose is inctact.
•
Make sure the mains cord is attached correctly and that it is not damaged.
The bathtub may only be used after it has been successfully and correctly installed.
On-Site Preparations
1.
½ inch hot and cold water connection, stopcock with a ¾ inch external thread for connecting nut (on-site
pre-shutoff device), incoming water pressure 1-5 bar.
2.
Mains connection 230V / 50Hz, 10A, or 110V / 60 Hz depending on model. Please note: All electrical
conduit, fitting and wiring to bath supplied and installed by a certified electrician in accordance with local
or applicable electric code as a minimum requirement. Main switch with signal lamp, main fuse and earth
circuit breaker are not included and must be supplied by others.
Installation of Thermostatic Mixer
1.
Rinse pipes according to DIN 19881.
2.
Attach connections to the water supply.
3.
The hot water supply has to be the left and the cold water supply on the right side. Check the connections
for any leaks and make sure the fittings are working properly.