www.extrememarquees.com.au 1300 850 832
STEP 3:
Assemble Ridge Connector with Roof Beams
Put Ridge Connector into Roof Beam and bolt together.
You have now completed one Bay, repeat the process until all
Bays are constructed.
STEP 4:
Elevate Frame
When two bays have been completed, stand up the first bay.
Once upright hold into position with two team members or secure
with ropes. Stand up second bay and move into position.
Diagram note: (b) 3m or 5m bays, refer to elevation diagram.
STEP 5 A:
Connect the Reinforcing Beam
Connect the two bays together
using the Frame Reinforcing
Beam and bolt together.
STEP 5 B:
Connect the Cross Brace
Refer to elevation diagram for
positioning of Cross Braces.
Fix the Cross Brace to the Corner
Uprights and bolt together.
For FS and FD series, they don’t have
cross bracing on side. Only 10m span
have roof cable.
Cross
Brace
Refer to the Elevation Drawing and Parts List to confirm
your method of construction for
Step 5.
Ridge Connector with Roof beams
Ridge Connector