![Exmark Z Turf Equipment Z-SPRAY Operator'S Manual Download Page 57](http://html1.mh-extra.com/html/exmark/z-turf-equipment-z-spray/z-turf-equipment-z-spray_operators-manual_2451280057.webp)
Maintenance
g027151
Figure 36
Viewed underneath machine
1.
Front of the unit
3.
Front tire
2.
Measure front outside
distance
4.
Measure rear outside
distance
5.
The front measurement should be approximately
1/4 inch (6.4 mm) larger than the rear
measurement. If adjustment is needed:
A.
Remove the front cover.
B.
Loosen the jam nuts at the rod ends.
g027152
Figure 37
1.
Jam nuts
C.
Rotate the steering rod to lengthen or shorten
the linkage. Adjust both the LH and RH
steering linkages equally.
Note:
The factory center-to-center distance
between the rod ball joint ends on the steering
linkage is 9.21 inches (23.3 cm).
D.
Tighten the jam nuts.
E.
Reinstall the front cover.
6.
Remove the long bolt from the steering control.
Spreader Pattern Control
Cable Adjustment
To adjust the spreader pattern control cable:
1.
Stop engine, wait for all moving parts to stop, and
remove key. Engage parking brake.
2.
Close the granular gate.
3.
Make sure the spread pattern control handle is
pushed down and locked at the control panel.
4.
Loosen the jam nut at the end of the cable.
g027205
Figure 38
1.
Jam nut
2.
Linkage rod
3.
Impeller shaft
4.
1/8 inch (3.2 mm) gap between ramp tooth and impeller
shaft
5.
Ramp tooth
57