TECHNICAL ACCEPTANCE
In order to commission the installed device for operation, do the following in witness
of a person authorised for technical acceptance:
Measure the battery voltage.
Measure the output voltage in the mains operating mode.
Test the UPS switching from mains to batteries without interruption of the load
power supply (if possible, test at the target load of the UPS circuit).
Measure the output voltage in the battery operating mode.
If a bypass is installed, train the personnel designated by the buyer in the bypass
operation.
Confirm the completed technical acceptance with the acceptance report and
release the necessary documentation (i.e. the warranty and the Instruction
Manual) to the buyer.