The lamp has to be replaced when it is damaged
or deformed due to the heat!
CAUTION!
Before replacing the lamp, unplug mains lead and let the lamp cool down (approx. 20 minutes).
During the installation do not touch the glass-bulbs bare-handed! Please follow the lamp manufacturer's
notes!
Do not install lamps with a higher wattage! Lamps with a higher wattage generate temperatures the device
was not designed for. Damages caused by non-observance are not subject to warranty.
For the installation, you need three 230 V/300 W R7S 117mm pole burner lamps.
During the operation, the lamp reaches temperatures of up to >1000° C.
Procedure:
Step 1:
Unscrew the fixation screws of the lamp service lid.
Step 2:
Remove the service lid.
Step 3:
If replacing the lamp, remove the old lamp from the lamp-socket.
Step 4:
Insert the new 230 V/300 W R7S 117mm pole burner lamp into the lamp-socket.
Step 5:
Replace the service lid and tighten the screws.
Do not operate this device with opened lamp service lid!
Rigging
The device can be installed on the ground or overhead.
Overhead rigging
DANGER TO LIFE!
Please consider the EN 60598-2-17and the respective national norms during the installation!
The installation must only be carried out by an authorized dealer!
The installation of the device has to be built and constructed in a way that it can hold 10 times the weight for 1
hour without any harming deformation.
The installation must always be secured with a secondary safety attachment, e.g. an appropriate catch net.
This secondary safety attachment must be constructed in a way that no part of the installation can fall down if
the main attachment fails.
When rigging, derigging or servicing the device staying in the area below the installation place, on bridges,
under high working places and other endangered areas is forbidden.
The operator has to make sure that safety-relating and machine-technical installations are approved by an
expert before taking into operation for the first time and after changes before taking into operation another
time.
The operator has to make sure that safety-relating and machine-technical installations are approved by an
expert after every four year in the course of an acceptance test.