7.2 Vertical installation
Fire dampers can be suspended by using threaded rods and a mounting profiles.
Load the suspension system depend on weight of the fire damper.
Damper can be suspended from the ceiling construction or supported above the ceiling
construction. Damper assembly procedures must be done so as all load transfer from the fire
separating constructions to the damper body is absolutely excluded. Back-to-back
air-conditioning piping must be hung or supported so as all load transfer from the back-to-back
piping to the damper is absolutely excluded.
Threaded rods longer than 1,5 m require fire-resistant insulation.
Threaded rod fixing to the ceiling construction - see fig. 83
Fig. 63 Suspension- vertical duct
Actuating mechanism is placed above the ceiling construction.
Actuating mechanism is placed under the ceiling construction.
Position:
1 Fire damper
2 Damping pad
3 Extension piece
4 Threaded rod
5 Mounting rail
6 Nut
7 U - Washer
8 Washer
9 Screw connection
10 Mounting profile
11 Mounting rail
12 Fire resistant board
Examples of using materials:
HILTI, SIKLA, MÜPRO etc.
Shown schemes of incorporation and damper are illustrative only!