Etrel Load Guard | User manual
|
Figure 34: Enabling the cluster service
In web interface of the charging station click on
Power management
and
then
Building power limits
. On the right the option
Load Guard installed
can be selected.
Figure 35: Connection with Load Guard is established
Serial number of the Load Guard must be written in the field
Serial
number
(in the presented case this number is 18430011). After that click
on
Save
and restart the charging station.
If the communication between Load Guard and charging station is
established, the
Communication status
will be
Connected
. The following
icon will be shown in the top right corner of the web interface:
The state
Connected
will also be shown in
Load Guard Communication
Status
.
Figure 36: Display of network state