9
BluesSystem Installation Manual
Supplies
The following supplies are included:
• (1) Junction box cover plate (available in round, square, or octagonal)
• (2) M4 screws for mounting the fixture to the junction box
• (1) Sealing gasket
• Wiring pigtail for power, ground, and control
The following supplies are not included (provided by others):
• Conduit and conduit fittings
• Junction box
Fixture Installation
Step 1:
Install conduit between the BluesSystem power supply and the fixture installation
location, following your installation wiring plan. It is acceptable to continue the wiring
run up to 10 fixtures per zone on a power supply.
Step 2:
Run wiring to the fixture, leaving approximately 8" (203mm) of wiring in the box for
future servicing as needed.
Step 3:
Align the mounting plate.
Step 4:
Align the provided gasket to the back side of the fixture.
Step 5:
Pull wiring through the mounting plate and gasket.
WARNING:
RISK OF DEATH BY ELECTRIC SHOCK! Failure to disconnect all power
to the system before installation, maintenance, cleaning or any other
system modification, could result in serious injury or death.
De-energize the main feed to BluesSystem and follow appropriate
Lockout/ Tagout procedures as described in NFPA Standard 70E. It is
important to note that electrical equipment such as relay panels, can
present an arc flash safety hazard if improperly serviced. This is due
to available large short circuit currents on the feeders of the
equipment. Any work on energized equipment must comply with
OSHA Electrical Safe Working Practices.