8
INSTALLATION
Proper installation can contribute materially to satis-
factory and troublefree operation of the cutting pack-
age. It is suggested that each step in this section be
studied carefully and followed as closely as possible.
A. INSPECTION AND PLACEMENT
1.
Having removed the shipping container inspect for
evidence of concealed damage which may not
have been apparent upon receipt of the unit. No-
tify the carrier of any defects or damage at once.
2.
Check the container for any loose parts. Check air
louvers on all panels of cabinet and holes through
the base are free of any packing materials that may
obstruct air flow through the power supply.
3.
The components in the HANDY PLASMA 125 con-
sole are: maintained at proper operating tempera-
tures by fan cooling. Air is drawn in through the
rear panel and then out the louvers in the front
panel. Locate the power supply in an open area
where air can circulate freely through the open-
ings. Allow at least one foot of clearance between
the power supply and wall or any other obstruc-
tion.
The area around the power supply should
be relatively free of dust, fumes, and excessive
heat.
B. PRIMARY INPUT ELECTRICAL CONNECTION
Precautionary measures should be taken to pro-
vide maximum protection against electrical shock.
Be sure that all power is off by opening the line
(wall) disconnect switch and by unplugging the
power cord to the unit when connections are made
inside the power supply.
1.
The HANDY PLASMA 125 is equipped with a 10-ft.,
3-conductor input power cable with a 115V plug.
Plug into standard 115 volt outlet.
SECTION
3
INSTALLATION
Fig. 3.1 - Handy Plasma 125 Interconnection Diagram
115V
20 amps
WORK CABLE (12-1/2’)
WORK
PT-34 TORCH w/15’ Lines
Earth Ground