Annual Maintenance
To assure the correct functioning of the control valve, the following items must be checked annually:
1.
Clean out injector.
2.
Clean brine refill flow control.
3.
Clean backwash flow control.
4.
Verify correct functioning of flow meter; clean impeller if necessary.
5.
Verify programming of timer; re-program timer if necessary.
6.
Measure the residual hardness; adjust mixing valve if necessary.
7.
Verify min and max. pressure; install pressure reducer if necessary.