Electronics Issues (Cont’d) 

Problems 

Possible Reasons 

Possible Solutions 

 

IS Barrier failure (For 330S 

analyzer series only) 

IS Barrier may need replacement. Consult 

Envent Engineering Ltd. 

 

Contaminants in sample 

chamber 

Clean sample chamber. Replace aperture 

and window if required. Contact Envent 

Engineering Ltd for replacement and 

assistance. 

Fault LED (Low 

H

2

S sensing 

Tape) 

New H

2

S sensing tape is 

required 

H

2

S Sensing tape requires change 

(Average of 2 to 3 days left, from the 

moment alarm goes off, for the tape to be 

completely used up). Refer to "H

2

S Sensing 

Tape Change Procedure" on page 35 or on 

sticker in the analyzers door.  

 

Low H

2

S sensing tape sensor 

failure 

If the alarm does not clear once a new H

2

sensing tape is installed, the low H

2

sensing tape sensor or its wires have failed 

and need to be replaced. Consult Envent 

Engineering Ltd to order a replacement.  

Low H

2

S sensing Tape Sensor Part #: 

330046A 

Fault LED (Low 

Pressure) 

Pressure of sample gas is 

lower than setpoint of pressure 

switch (factory set to 10 psi 

descending) 

Inspect the sample inlet upstream to 

troubleshoot the problem. 

 

 

 

Pressure switch failed 

If pressure is above 10 psi and alarm 

continuous, the pressure switch setpoint 

might have changed. Set back to 10 psi 

descending. Also, check pressure switch 

wiring 

If the problem persists, pressure switch 

might need replacement. Contact Envent 

Engineering Ltd. 

 

Pressure regulator failed 

The problem might be coming from the 

pressure regulator. Troubleshoot and 

consult Envent Engineering Ltd. 

Fault LED 

(Oven Fail) 

Fuse not installed. 

Fuse for furnace does not come installed in 

the controller board. Please check spare 

fuse bag and install fuse. 

 

Oven not working properly 

Oven failed and temperature has dropped 

below the optimal temperature. Please 

consult Envent Engineering Ltd. 

Blank Display 

Contrast needs adjustment 

Change contrast by turning the 

potentiometer in the display board. 

Continued on next page

 

 

 

 

 

Summary of Contents for 330S-Ex

Page 1: ...Envent Engineering Ltd Hydrogen Sulfide Analyzer Model 330S Ex Model 330SDS Ex User s Manual Revision 1 21 Jan 2022...

Page 2: ......

Page 3: ...SDS 10 INSTALLATION 11 Receiving the Analyzer 11 Unpacking the Analyzer 11 Standard spare parts for 330S Ex H2S analyzers 11 Installation procedure Start up 12 Installation Requirements 13 Electrical...

Page 4: ...g Tape Change Procedure 35 Sample Conditioning System Cleaning Procedure 36 Material List 36 Procedure 36 TROUBLESHOOTING 38 APPENDICES 48 Recommended Spare Parts List 48 Sealing Compound For sealing...

Page 5: ...igure 9 Space Requirements for 330SDS Ex with Total Sulfur Option Backpan size may vary 20 Figure 10 Recommended Venting for 330S Ex Same as the 330SDS Ex H2S Analyzer 22 Figure 11 AO 4 20 mA Output W...

Page 6: ...n furnace for total sulfur measurements Throughout this document will be referring to the models 330S Ex However the information applies equally to the 330SDS Ex Dual sensor unless otherwise stated To...

Page 7: ...arranty The foregoing warranty shall not apply to defects arising from Improper or inadequate maintenance by the user Improper or inadequate unpacking or site preparation installation Unauthorized mod...

Page 8: ...of hazards that could result in major injury or death Description of hazards that could result in minor injury or property damage Description of important information regarding safety of personal and...

Page 9: ...ct selection safety and warning requirements for the application If the equipment is used in a manner not specified by Envent Engineering Ltd the protection provided by the equipment may be impaired D...

Page 10: ...flow from this cover can indicate the possibility that a failed primary seal condition could exist in the pressure switch If the 330S Ex or the 330SDS Ex has a total sulfur enclosure ensure its caps a...

Page 11: ...outputs loop power required optional 4 20mA powered output boards are available Serial Communication 1 RS 232 Modbus protocol 3 RS 485 Modbus protocol One RS 485 for remote display option Ethernet por...

Page 12: ...ulfur compound is present in the sample stream The H2S reaction is visibly evident by a brown stain directly on the H2S sensing tape COOH CH PbS COO CH Pb S H O H 3 2 3 2 2 2 The electronics built int...

Page 13: ...ly Pressure should be kept at a constant 15 psig The lowest pressure found to be tolerable for proper H2S measurement is 0 5 psig Flow must be kept at a constant flow of 2 cm between 100 200 cc min A...

Page 14: ...r the H2S reading for that cycle From stage 2 to 4 the H2S value starts increasing as the millivolt value drops from exposure to H2S This stage is called RRA Analysis The RRA stands for Rapid Response...

Page 15: ...ame time e g Sensor 1 0 20 ppm H2S Sensor 2 0 200 ppm H2S The analysis cycle process is the same per sensor as explained earlier in this section however some extra algorithms have been implementing to...

Page 16: ...330SDS Ex H2S analyzer with a standard Sample conditioning system weights approximately 105 lb 48 kg Unpacking and transporting requires a minimum of two persons 3 Make sure the start up kit is compl...

Page 17: ...l 7 Wire the power analog outputs and discrete outputs from the analyzer 8 Tube the Sample inlet sample sweep and sample vent lines from the analyzer 9 Ensure there is enough H2S Sensing tape 10 Insta...

Page 18: ...rating shall be used e g 120 VAC rated solenoid the analyzer shall be powered with only 120 VAC and not 240 VAC The power consumption for a VDC analyzer is 3 Watts and for a VAC is 5 Watts For the to...

Page 19: ...Envent Engineering Ltd Page 14 Revision 1 Earth Connections Entry Specifications Space Requirements Figure 3 Enclosure Entries Earth Connections...

Page 20: ...Envent Engineering Ltd Page 15 Revision 1 Figure 4 Space Requirements Entry Specifications for Model 330S Ex No Backpan...

Page 21: ...Envent Engineering Ltd Page 16 Revision 1 Figure 5 Space Requirements Entry Specifications for Model 330SDS Ex No Backpan...

Page 22: ...Envent Engineering Ltd Page 17 Revision 1 Figure 6 Space Requirements for 330S Ex with Standard Backpan Size may vary...

Page 23: ...Envent Engineering Ltd Page 18 Revision 1 Figure 7 Space Requirements for 330SDS Ex with Standard Backpan Size may vary...

Page 24: ...Envent Engineering Ltd Page 19 Revision 1 Figure 8 Space Requirements for 330S Ex with Total Sulfur Option Backpan size may vary...

Page 25: ...Envent Engineering Ltd Page 20 Revision 1 Figure 9 Space Requirements for 330SDS Ex with Total Sulfur Option Backpan size may vary...

Page 26: ...d to reduce the pressure of the sample The lower pressure will improve the response time of the analyzer Refer to Figure 10 It is advisable that the probe not be installed on a vertical pipe Sample in...

Page 27: ...ep The standard sample tubing material is 1 4 316 stainless steel however 1 8 0 3175 cm stainless steel tubing can be used if the response time is critical refer to Table 2 Tube Size Tube Gauge ID ID...

Page 28: ...is section Please refer to the total sulfur and dilution manuals Analog Outputs The H2S controller board has two isolated loop power 4 20mA outputs which can be set up for different variable outputs L...

Page 29: ...AO 4 20 mA Output Wiring Options Sample Chamber The sample chamber is the component that allows the H2S sample to come in contact to the H2S sensing tape which in turn is read by the sensor block The...

Page 30: ...refer to Figure 12 The window keeps a clear view for the LED and the photodiode to work properly and isolates them from the sample gas The rubber gasket seals the Sample Chamber compartment preventin...

Page 31: ...nvent Engineering Ltd to purchase an aperture strip Remember gain and span values on analog outputs will have to change based on new range application Please re calibrate analyzer Refer to H2S Gas Cal...

Page 32: ...to create mold and fungus overtime Moreover the freezing point for water is 0 C and for 5 Acetic Acid is 2 C making it more reliable under freezing temperatures For the SDS models the humidifier has...

Page 33: ...alyzer reading can be affected by positive or negative pressure on the sample vent line This can be caused by strong winds blowing across or directly into the vent or by mechanical venting exhaust fan...

Page 34: ...ocity and drying effect of the sweep gas The eductor vent can be retrofitted to existing analyzers In normal conditions the eductor makes a noise similar to a gas leak This noise is normal and it is d...

Page 35: ...the display buttons and LED s are described in table Table 4 Table 5 Button Description Function Bypass Used to inhibit all analyzer alarms to a non alarm state and sets the analog 4 40 mA output to...

Page 36: ...spare Fault Illuminates when there is a fault in the Analyzer Fault is used for Board temperature Sensor High Low Low H2S sensing tape sensor Pressure switch etc LED 1 to 4 Green LEDs that can be use...

Page 37: ...s the Menu Set button until Mtr Run is displayed Press the right arrow the H2S sensing tape will advance for approximately 10 seconds 5 Press the Menu Set button until mV is displayed mV If the mV rea...

Page 38: ...minutes confirm the analyzer reads below the H2S alarm set points Remove the analyzer from bypass mode by pressing the bypass button Verify the Bypass LED turns off Alarms are armed after removing th...

Page 39: ...e 34 Revision 1 11 Confirm the analyzer reads below the H2S alarm set points 12 Remove the analyzer from bypass mode by pressing the bypass button Verify the Bypass LED turns off Alarms are armed afte...

Page 40: ...s are tight Ensure that the flow meters humidifier tubing and sample chamber tubing are free of liquid or particulate contamination If the sample conditioning system is flooded with liquid refer to Sa...

Page 41: ...fittings x2 MIP 4 Humidifier replacement plug 06349 40 Black 1 8 male female elbow LT 2 4 1 4 x 11 0 635 x 27 94 cm Tubing for sample chamber to humidifier LT 2 4 1 4 x 10 0 635 x 25 4 cm Tubing for f...

Page 42: ...ced if it appears contaminated Disassembly of the pressure regulator and solenoids in the field is not advised Consult the factory if the regulator or solenoid appears contaminated 4 Re assemble Stain...

Page 43: ...be 316 stainless steel 3 8 0 9525 cm or larger on a downward slope Possible heat trace required Analog input 2 jumper removed Re install jumper in Analog Input across 4 20 4 20 on the controller board...

Page 44: ...analyzer Refer to H2S Gas Calibration on page 36 Contaminants or liquid carry over in sample conditioning system If contaminants or liquid has carried over the sample system refer to page 36 Higher t...

Page 45: ...trations and re connect the tubing to the fittings on canister lid Contact Envent engineering Ltd for replacement if required Total Sulfur s Hydrogen flow was decreased at the flow meter Total Sulfur...

Page 46: ...Leaking it needs to either be repaired or replaced Consult Envent Engineering Ltd Sensor sensor wire failure Re zero the sensor block Refer to Re zero Sensor Procedure on page 33 If procedure fails s...

Page 47: ...ted in groove of sample chamber Overlapping Stains This is normal in the 1st 1 4 of a new H2S sensing tape It should not cause any reading problems If it is causing reading problems the stop threshold...

Page 48: ...o do a motor run Display Press Menu Button until MTR Run Press right button This will activate the motor and move the H2S Sensing tape for a few seconds The alarm should clear Faulty Sensor Sensor nee...

Page 49: ...ng Ltd to order a replacement Low H2S sensing Tape Sensor Part 330046A Fault LED Low Pressure Pressure of sample gas is lower than setpoint of pressure switch factory set to 10 psi descending Inspect...

Page 50: ...age rating Make sure to use the appropriate voltage to power the analyzer DC controller boards can be powered with 12 24 VDC and AC controller boards can be powered with 110 to 240 VAC Keep in mind th...

Page 51: ...that the analyzer is below or above like temperature setpoint those setpoint values Sample Conditioning System Issues Problems Possible Reasons Possible Solutions Liquid Carried over in SCS Sample to...

Page 52: ...C if 5 acetic acid is used Do not expose analyzer to temperatures below 0 degress C or 2 degress C Humidifier leaking liquid The humidifier body cracked Could be due to extreme temperature changes A...

Page 53: ...110 1 or 2 for SDS Aperture Strip Associated to measurement range 330130 1 4 liter Containers of Acetic Acid 330133XS 12 300 91 44 m Lead Acetate Tape H2S Sensing Tape 330406 1 Box of 10 Micro Filter...

Page 54: ...Envent Engineering Ltd Page 49 Revision 1 Sealing Compound For sealing fittings in Hazardous Locations...

Page 55: ...Envent Engineering Ltd Page 50 Revision 1...

Page 56: ...Envent Engineering Ltd Page 51 Revision 1...

Page 57: ...Envent Engineering Ltd Page 52 Revision 1...

Page 58: ...Envent Engineering Ltd Page 53 Revision 1...

Page 59: ...Envent Engineering Ltd Page 54 Revision 1...

Page 60: ...Envent Engineering Ltd Page 55 Revision 1...

Page 61: ...Envent Engineering Ltd Page 56 Revision 1...

Page 62: ...Envent Engineering Ltd Page 57 Revision 1...

Page 63: ...Envent Engineering Ltd Page 58 Revision 1...

Page 64: ...Envent Engineering Ltd Page 59 Revision 1...

Page 65: ...Envent Engineering Ltd Page 60 Revision 1...

Page 66: ...Envent Engineering Ltd Page 61 Revision 1 Safety Data Sheet for H2S Sensing Tape...

Page 67: ...Envent Engineering Ltd Page 62 Revision 1...

Page 68: ...Envent Engineering Ltd Page 63 Revision 1...

Page 69: ...Envent Engineering Ltd Page 64 Revision 1...

Page 70: ...Envent Engineering Ltd Page 65 Revision 1...

Page 71: ...o Rev 1 1 on this user manual means that content changes will not affect or contradict ATEX IEC certification documentation thus the notified body does not need to be informed of the changes for insta...

Reviews: