A )  Make sure that the main load center wires are de-energized until you 

have secured the CT wires in the terminal blocks.

B )  Before running the CT wires through the conduit, use colored tape to 

mark one of the CTs and the free end of its wires.

C )  For the marked CT wires, connect the white and blue wires to the white 

and blue “C1” terminals.

D )  For the unmarked CT wires, connect the white and blue wires to the 

white and blue “C2” terminals.

E )  Tighten all connections to 5 in-lbs.
F )  Clamp the marked CT on the load center feed wire Line 1 (matching the 

Envoy’s “L1” voltage terminal) 

with the CT arrow pointing toward the 

load (away from the grid)

.

G )  Clamp the unmarked CT on the load center feed wire Line 2 (matching 

the Envoy’s “L2” voltage terminal) 

with the CT arrow pointing toward 

the load (away from the grid).

      Install CTs for Consumption Metering (optional)

The IQ Envoy inside the IQ C is pre-wired at the terminal blocks for power and production metering connections. One solid-core current transformer (CT) 
is provided for revenue grade production metering. You can install two optional split-core CTs to provide consumption metering. To do this, you must create a 
protected route using conduit for the CT wires from the main load center to the IQ Envoy. If you need to extend the wires, refer to the 

Enphase IQ Envoy Installation 

and Operation Manual 

at: 

enphase.com/support.

Notes

It is important to match CT and sense voltage phases. To proper-

ly measure power and energy, CT inputs must align with the respective 

voltage inputs. Be sure to consistently identify and match the two AC 

lines at two points: the main load center feed and the Envoy. Wire colors 

(typically black and red) may not always consistently identify Lines 1 

and 2. If in doubt, use a multimeter to check. 

6

Note

Because of variance in load center design and main power feed, there may not always be enough space to install consumption metering CTs.

DANGER! 

Risk of electrocution! Do not install CTs when cur-

rent is flowing in the sensed circuit. Always install CT wires 

in the terminal blocks before energizing the sensed circuit.

Load Center

To Grid

From IQ Combiner

IQ Envoy Terminal Block

Relay contacts

(if needed)

UP TO 250 Vac.

100A 0.5V

45-66Hz

whit

e

blue

Not used    

whit

e

blue

P1

C1 C2

1

2

3

4

NO

 Ref

Common

C

Digital Input

Relay

PD, B300

OVC II

 

L1

L2

N

CU, 75C, 14AWG MIN

MEAS CAT III

OVC III

Production  |  Consumption

Consumption CTs

The arrows must point 

toward the load — away 

from the grid.

DANGER! 

Risk of electric shock. Always de-energize the load 

center before beginning wiring.

     

Energize and Update the IQ Envoy

A )  Close the terminal block door, and secure it with the screw.
B )  Re-install the clear plastic deadfront. Start all of the screws, but do not 

completely tighten them. Once all screws are partially tightened, go back 

and tighten each one completely.

C )  Turn off the DG breaker(s).
D )  Reinstall the IQ C door.
E )  Turn on the circuit feeding the combiner.
F )  On the IQ Envoy, if the AP Mode LED is not lit, press the AP Mode button. 
G )  On your mobile device, go to Settings and join the Wi-Fi network “Envoy_nn-

nnnn” (where “nnnnnn” equals the final six digits of the Envoy serial number).

H )  The app informs you if the software on the Envoy is not the latest version 

by displaying the Envoy Software Update message. If the app displays this 

message, follow the on-screen instructions to update the Envoy.

I )  For a short period (5-10 minutes), you must keep your mobile device 

near the Envoy. Follow the on-screen instructions while the update 

takes place. 

The update may take up to 20 minutes. The Envoy reboots several times 

during the update and the LEDs light up in varied sequences until the update 

is complete.
Once the update is finished and the PV system is installed, the Envoy is 

ready for Installation Part 2.
All four LEDs flash amber during boot up (approximately 3 minutes). When 

boot up is complete, the Device Communications LED 

 lights solid 

amber, indicating that devices are not yet detected.

7

Summary of Contents for IQ Combiner+

Page 1: ... that installation of the Combiner has two parts To ensure successful device detection complete Part 2 after install ing any Enphase IQ Microinverters and or Enphase AC Battery ies Note If needed you can find an installation map at the back of any Enphase Microinverter Quick Install Guide Model X IQ AM1 240 2 IQ Envoy Display and Controls Network Communications LED Green when IQ Envoy is connected...

Page 2: ... sized to meet local code requirements and voltage drop rise considerations B Bring in the wires from each AC branch circuit C Connect the ground green or green yellow to the ground busbar D Pass the L1 conductors from each PV branch circuit through the produc tion CT in the same direction as the arrow on the side of the CT E If you use the fourth Battery PV breaker position for PV you must route ...

Page 3: ...nstall consumption metering CTs DANGER Risk of electrocution Do not install CTs when cur rent is flowing in the sensed circuit Always install CT wires in the terminal blocks before energizing the sensed circuit Load Center To Grid From IQ Combiner IQ Envoy Terminal Block Relay contacts if needed UP TO 250 Vac 100A 0 5V 45 66Hz white blue Not used white blue P1 C1 C2 1 2 3 4 NO Ref Common C Digital...

Page 4: ...file settings 8 INSTALLATION Part 2 You must complete Installation Part 2 after installing any Enphase IQ Microinverters and or Enphase Battery ies Detect Devices A Turn on the DG breaker s B Use one of the following methods to detect devices Enphase IQ Microin verters and or Enphase Batteries Method A Provision devices with Installer Toolkit Use the Installer Toolkit mobile app to configure the I...

Page 5: ...Toolkit mobile app to see which devices are not com municating Check that the circuit breaker s in the IQ Combiner for the PV array are in the ON position Verify that the PV modules are connected to the microinverters Verify the PV module DC voltage is within the allowable range for the microinverter c Power production issues If the Power Production LED lights solid amber check the Installer Toolk...

Page 6: ...eded WARNING Before installing or using the IQ Combiner read all instruc tions and cautionary markings in the technical description and on the equipment WARNING Use the circuit breakers in the Enphase IQ Combiner only for serving Enphase equipment No other loads are allowed FCC Statement This equipment has been tested and found to comply with the limits for a Class B digital device pursuant to par...

Reviews: