Instead, if the installation consisted of a horizontal vent coming out at the
back of the stove on a total distance of 4 feet, followed by a tee and a 6-
foot vertical rise, it would be acceptable. The termination is within the
allowable configuration zone on the chart since it would have at least one
foot of vertical rise for each foot of horizontal run. Furthermore, the total
vertical rise is at least 3-feet high.
WARNING: To reduce the risk of smoke spillage there should always be at
least one foot of vertical rise for each foot of horizontal run. In all cases, at
least 3 feet of vertical rise is needed.
Summary of Contents for Cambridge EP00075
Page 64: ...64 Cambridge Pellet Stove Installation and Operation Manual 10 WIRING DIAGRAM ...
Page 73: ...Cambridge Pellet Stove Installation and Operation Manual 73 ...
Page 74: ...74 Cambridge Pellet Stove Installation and Operation Manual ...
Page 75: ...Cambridge Pellet Stove Installation and Operation Manual 75 ...
Page 76: ...76 Cambridge Pellet Stove Installation and Operation Manual ...
Page 77: ...Cambridge Pellet Stove Installation and Operation Manual 77 ...
Page 78: ...78 Cambridge Pellet Stove Installation and Operation Manual ...
Page 79: ...Cambridge Pellet Stove Installation and Operation Manual 79 ...