Operation Overview
The UV-MAX is designed to operate in the following manner:
Start Sequence
1. Locate unit in unoccupied space positioned for operation
2. Plug system into power supply
3. Review display for
“Start Cycle” state
4. Turn on system
5. Evacuate space
Audio and Visual Indicators
1. Audio Alarm
a. Once Started: Short warning beeps increasing in frequency
b. During Process: Long stroke beeps
c. Process Complete: Three short beeps (no beep thereafter)
2. Visual Indicator
a. Red Light
– Warning, get out process running
b. Green Light
– Safe/Process complete
3. Display of System
a. Operations
b. Controls
c. Indication of System Functions