Installation
ASP Station 2000 RPS20B
18
Hauser
5.1.3
Installation site
1
2
3
4
A0022681
1.
Correct
The suction line must be routed with a downward gradient to the sampling point.
2.
Incorrect
The sampler should never be mounted in a place where it is exposed to aggressive
gases.
3.
Incorrect
Avoid siphoning effects in the suction line.
4.
Incorrect
The suction pipe should never be routed with an upward gradient to the sampling
point.
Note the following when erecting the device:
• Erect the device on a level surface.
• Protect the device against additional heating (e.g. from heaters).
• Protect the device against mechanical vibrations.
• Protect the device against strong magnetic fields.
• Make sure air can circulate freely at the side panels of the cabinet. Do not mount the device
directly against a wall. Distance from wall on left and right: min. 150 mm (5.9").
• Do not erect the device directly above the inlet channel of a wastewater treatment plant.
5.1.4
Connection for suctioning samples