Introduction
2
2.0
I
NTRODUCTION
2.1
References
This document must be used together with site specific documentation and documentation for other
parts of the system.
2.2
Pre-Installation Checks
• Check the received materials to be sure all required assemblies and parts have been received. If
you discover any external damage, report it to the shipping company and your local Emerson rep-
resentative.
2.3
Packing List
• User manual (this document)
• Liebert XDR module
2.4
Installation Considerations
The Liebert XDR is designed for attachment to the rear of computer cabinets in the data center. See
4.0 - Mechanical Considerations
for details.
2.4.1 Room Preparation
The room should be well-insulated and must have a sealed vapor barrier. The vapor barrier in the
ceiling and walls can be a polyethylene film. Paint on concrete walls and floors should contain either
rubber or plastic.
Outside or fresh air should be kept to a minimum when temperature and humidity must be tightly
controlled. Outside air adds to the cooling, heating, dehumidifying and humidifying loads of the site.
Doors should be properly sealed to minimize leaks and should not contain ventilation grilles.
NOTE
The vapor barrier is the single most important requirement for maintaining environmental
control in the conditioned space.