introduction

Scope of the Manual

This Instruction Manual covers Installation and 

Maintenance for the HSRL Series regulators, which 

are second stage regulators used on LP-Gas vapor 

service applications.  They are not to be used on  

liquid service.

Description

The HSRL Series regulators are second stage low 

pressure regulators, provide low pressure, inches of 

water column, delivery pressures.  They are normally 

set at 11-inches w.c. / 27 mbar pressure.  They have 

high capacity internal relief valve construction.   

installation

!

WaRninG

all vents should be kept open to 

permit free flow of air in and out of 

the regulator.  Protect vent openings 

against the entrance of rain, snow, ice 

formation, paint, mud, insects, or any 

other foreign material that could plug 

the vent or vent line.

LP-Gas may discharge to the 

atmosphere through the vent.  an 

obstructed vent which limits air or 

gas flow can cause abnormally high 

pressure that could result in personal 

injury or property damage.  Failure to 

use a vent line on indoor installations 

can cause a hazardous accumulation 

of gas which could result in personal 

injury or property damage. 

General installation instructions

Before installing the regulator:

•  Check for damage, which might have occurred 

 

in shipment.

•  Check for and remove any dirt or foreign material, 

which may have accumulated in the regulator body.

• 

Replace old pigtails.  Blow out any debris, dirt or 

copper sulfate in the copper tubing and the pipeline.

• 

Apply pipe compound to the male threads of the 

pipe before installing the regulator.

•  Make sure gas flow through the regulator is in the 

same direction as the arrow on the body.  “Inlet” 

and “Outlet” connections are clearly marked.

Figure 2.  Regulator with Vent Pointed Down

3 FEET / 

0.91 meter

VENT POINTED DOWN

3 FEET / 

0.91 meter

VENT POINTED DOWN

Summary of Contents for Fisher HSRL Series

Page 1: ...standards and regulations of the LP Gas industry should install and service this equipment Things to tell the gas customer 1 Show the customer the vent or vent assembly or vent tube Stress that this opening must remain unobstructed at all times Tell the customer to check the vent opening after a freezing rain sleet storm or snow to make sure ice has not formed in the vent 2 Show the customer the s...

Page 2: ...mate Weight 5 5 pounds 2 5 kg 1 The pressure temperature limits in this Instruction Manual or any applicable standard limitation should not be exceeded Orifice Size Wide Open Cg FOR RELIEF SIZING MAXIMUM OPERATING INLET PRESSURE TO OBTAIN GOOD REGULATING PERFORMANCE Inch mm psig bar 3 8 9 5 105 30 2 1 1 2 13 185 20 1 4 Table 1 Maximum Operating Inlet Pressure Table 2 Relief Performance Orifice siz...

Page 3: ...scharge to the atmosphere through the vent An obstructed vent which limits air or gas flow can cause abnormally high pressure that could result in personal injury or property damage Failure to use a vent line on Indoor Installations can cause a hazardous accumulation of gas which could result in personal injury or property damage General Installation Instructions Before installing the regulator Ch...

Page 4: ...ugh above ground level at least 18 inches 45 cm so that rain splatter cannot freeze in the vent Regulators Subjected to Heavy Snow Conditions Some installations such as in areas with heavy snowfall may require a hood or enclosure to protect the regulator from snow load and vent freeze over Horizontally Installed Regulators Horizontally mounted regulators such as found in single cylinder installati...

Page 5: ... Series Figure 4 Basement Installation TO APPLIANCE VENT ASSEMBLY VENT OPENING MUST BE AT LEAST 3 FEET 0 91 meter HORIZONTALLY FROM ANY BUILDING OPENING BELOW IT VENT LINE BASEMENT FROM FIRST STAGE REGULATOR ...

Page 6: ... wear or damage that may occur from external sources these regulators must be inspected and maintained periodically The frequency of inspection and replacement of the from the regulator s internal relief valve Vent lines should be at least 3 4 inch NPT pipe or 3 4 inch NPT size Gray PVC Schedule 40 Rigid Non metallic Electrical Conduit for above Ground Service per Underwriters Laboratories UL 651 ...

Page 7: ...derground systems and in areas that are subject to sea salt coastal atmospheres should be inspected annually for external and internal corrosion and may require replacement sooner Refer to Fisher Bulletin LP 32 for additional information Water inside Regulators from Floods or Weather Replace any regulator that has been flooded has had water in the spring case or shows evidence of external or inter...

Page 8: ... services described herein or their use or applicability We reserve the right to modify or improve the designs or specifications of such products at any time without notice Emerson Process Management Regulator Technologies Inc does not assume responsibility for the selection use or maintenance of any product Responsibility for proper selection use and maintenance of any Emerson Process Management ...

Reviews: