Instruction Manual Supplement
D103401X012
ED, ES, ET, EW, EZ, HP Valves
November 2017
11
Appendix A
Sample Startup Checklist
This appendix provides a Sample Startup Checklist for a Fisher ED, ES, ET, EW, EZ, or HP valve. A startup checklist will
provide guidance during the final control element's emplo
yment.
Start
-
Up Checklist
The following checklist may be used as a guide to employ the ED, ES, ET, EW, EZ, or HP valve in a safety critical SIF
compliant to IEC61508.
#
Activity
Result
Verified
By
Date
Design
Target Safety Integrity Level and PFD
AVG
determined
Correct valve mode chosen (Failclosed, Failopen)
Design decision documented
Pneumatic compatibility and suitability verified
SIS logic solver requirements for valve tests defined and documented
Routing of pneumatic connections determined
SIS logic solver requirements for partial stroke tests defined and
documented
Design formally reviewed and suitability formally assessed
Implementation
Physical location appropriate
Pneumatic connections appropriate and according to applicable codes
SIS logic solver valve actuation test implemented
Maintenance instructions for proof test released
Verification and test plan released
Implementation formally reviewed and suitability formally assessed
Verification and Testing
Electrical connections verified and tested
Pneumatic connection verified and tested
SIS logic solver valve actuation test verified
Safety loop function verified
Safety loop timing measured
Bypass function tested
Verification and test results formally reviewed and suitability formally
assessed
Maintenance
Tubing blockage / partial blockage tested
Safety loop function tested