Introduction
This quick installation guide provides information on Copeland
™ EazyCool CO
2
refrigeration units and
describes the first steps for successful commissioning. It is not intended to replace the application guidelines,
to explain the functionality of the refrigeration unit or to help optimize the system parameters.
2
First steps
WARNING
Hot surfaces! Burning!
If the temperature on the bottom of the compressor (crankcase)
is below 20°C, the crankcase heater is automatically activated. Do not touch the
crankcase heater.
When the low-pressure side piping has been finalized and the electrical supply has been connected by
qualified personnel, please follow the steps below in preparation for commissioning:
Safety:
✓
Verification of necessary safety devices in the system
✓
Visual inspection of the refrigerant pipes and especially of all connections
✓
Visual inspection of the electrical wiring of the supply line
✓
Checking the refrigeration unit and connected cooling stations for damage of any kind
✓
Ensuring that no section of the system is under safety charge with dry air
Functionality:
✓
Switch on the device main switch (Q01)
✓
Switch on the disconnector for the single-phase power supply (F2)
✓
Switch on the safety chain transformer isolator switch (F5)
✓
Switch on the disconnector for the crankcase heater (F4)
✓
Switch on the RCCB for online monitoring (F1.1 = power supply to the router), if available
Figure 1: Switch on control system & small electrical components