5.3 MACHINE BREAK-IN
Although there are no operational restrictions on the
Portable Generator when used for the fi rst time, it is
recommended that the following mechanical items
be checked:
A. After operating for 1 hour:
1. Re-torque all fasteners and hardware.
2. Check condition of all electrical connec-
tions.
3. Check fl uid levels. Top up as required.
B. After operating for 10 hours:
1. Repeat steps 1 through 3 listed above.
(Section A)
2. Change engine oil.
3. Go to the normal servicing and mainte-
nance schedule as defi ned in the Mainte-
nance Section.
5.4 PRE-OPERATION CHECKLIST
Effi
cient and safe operation of the Wallenstein Port-
able Generator requires that each operator reads
and understands the using procedures and all
related safety precautions outlined in this section.
A pre-operation checklist is provided for the opera-
tor. It is important for both the personal safety and
maintaining good mechanical condition that this
checklist is followed.
Before operating Portable Generator and each time
thereafter, the following areas should be checked
off :
1. Check engine fl uid levels. Top up as required.
2. Check all electrical connections. Replace, re-
pair or clean as required.
3. Make sure that all guards and shields are in
place, secured and functioning as designed.