background image

 

 

Quick start instructions 

 
 
 
 
Place operator in correct position (Pinion wheel to be 
parallel to the gate and stepped out to allow for width 
of rack once it is mounted onto the gate frame). Mark 
out fixings and fix operator to the concrete pad. 
 
 
 

 

 
Fix rack to the gate frame keeping 1mm-2mm clearance 
between the rack teeth and Pinion wheel 
 

 
 
 
Once the rack is fixed move the gate and sight the 
rack moving over the pinion wheel, check that most of 
the pinion wheel meshes with the rack. Make sure 
rack runs freely over the pinion wheel, any tights 
spots should be corrected by adjusting the rack height. 
Check the operator is firmly bolted down to the 
concrete pad. 
 
 

 
 
Ensure stops are installed on the gate for the fully closed and 
fully open positions. 
 

 

 
 
 
 
 
 
Connect required P.E Beams.  
 
Limit switches can be used in 2 different configurations 

1.  Limit switch initiates ramp down and the gate stops as per ramp down time.  

2.  Limit switch initiates slow speed and the gate stops on slow speed overload after hitting the end 
stoppers. 
 
Follow the on screen instructions to commission the gate.   
 
 
 

 

   

 

 