The basic 

components

 for an electric energy heating system typically include: 

 

1.

 

Electric Mini-Boiler itself – covered by this manual. 

2.

 

Thermostat hookup control – covered by this manual. 

3.

 

Plumbing kit or piping material at the boiler itself – can be ordered as a kit, reference catalog number 
EMB-PK. 

a.

 

These items are shown on plumbing installation drawing BX305. 

4.

 

Circulating pump – typically sized for head pressure and system flow requirement, typical catalog 
number EMB-P2.  

5.

 

Radiant heat devices/components. 

 

APPROVED TUBING/PIPING 

 

When plumbing this boiler and its peripheral parts to the radiant floor loop system, all plumbing parts and/or 
tubing must be sealed to prevent entrance of oxygen. 

 

 

Use only tubing or polyethylene tubing with oxygen Diffusion Barrier (ie. PEX). 

 

SYSTEM OR WATER FLOW 

 

In order to prevent hi-limiting and assure full 20+ years parts life, the piping system/basic plumbing/circulator 
pump must be arranged to provide flow greater than minimum GPM shown in Table 1.  If zoned system, this 
applies when the smallest zone is operating. 

 

TABLE 1 - ELECTRO-BOILER SPECIFICATION 
240 volts, 60 Hz, single phase 
 

Model 

Btuh 

Rating 

Amp 

Stages 

Min. GPM for 160° F 

and above* 

Min. GPM for 144° F 

and below 

EMB-H-5 15,000 5 

kW 18.7A 

.5 

EMB-H-7 24,000 7 

kW 29.1A 

.5 

EMB-H-9 31,000 9 

kW 37.5A 

.5 

 

*Note: If less than 1 GPM is possible in high temp. mode, suggest using primary/secondary piping to increase 

flow rate through boiler, or consider installing zone controller EB-5415A (see page 2 for details). 

 

MULTIPLE ZONES AND RADIANT TEMPERATURES 

 

Same water temperature all zones – 

in this case the system can be setup as one pump with the water circulated 

through the boiler and directly to a manifold containing the various zone valves.  Although this model series has 
a built-in outlet sensing and controller mechanism for staging the elements, also consider the next section, Zone 
Controller.  If not using zone controller, the end switches of all of the zone valves are paralleled and directly 
control R and W to turn on the boiler. 

 

Various water temperature requirements – 

if this is the case, a primary loop with mixing valve for the 

various zone temperature requirements is necessary.  Injection pump techniques can also be used.  However, 
usually injection pump techniques come with a controller which is designed to protect a gas boiler from cool 
water return.  This is simply not needed and a duplication with the temp. sensing controller within this Electro-
boiler and the injection pump controller will be of no benefit within the operating system.  The zone valve/zone 
pump control strategy must be wired to provide the boiler “R and W” contact closure and the primary pump is 
connected to the boiler pump contacts.  This assures the primary pump is active and running whenever the boiler 
is turned on via contact closure on “R and W”.  At least one zone must be open before turning on the primary 
pump/Electro-Boiler.  Do not design a system where the Electro-Boiler is supposed to operate as a “hot boiler” 
based upon its outlet sensor without the primary pump circulating water, minimum .5 GPM is required. 

 

Summary of Contents for EMB-H-5

Page 1: ...s outdoor reset you should consider using model EB MO series Primary application is any hydronic water heating system high or low temperature systems where reduced flow or radiation can cause overheat conditions example zones However if it is a mixture of large and small zones the sudden capacity and flow changes may cause some internal timing over temp conditions This series is equipped for load ...

Page 2: ...ntrol 2 Zone Controller 2 Safety Temperature Control 2 Room Thermostat Placement 2 Water Flow Calculation 2 Installation Requirements 3 Electric Supply 3 Clearances 3 Mechanical Installation 4 Electrical Hookup 5 Water Fill Procedure 6 Operational Tips 8 Troubleshooting Helps 9 Drawings BX305 BH310 UAW411 BL001 XX017 ...

Page 3: ... consider installing zone controller EB 5415A see page 2 for details MULTIPLE ZONES AND RADIANT TEMPERATURES Same water temperature all zones in this case the system can be setup as one pump with the water circulated through the boiler and directly to a manifold containing the various zone valves Although this model series has a built in outlet sensing and controller mechanism for staging the elem...

Page 4: ...r tubing is under the concrete or within the sand base The controlling thermostat must have a remote bulb and this remote bulb must sense the concrete slab temperature slab stat Coordinated with the concrete pour install a PVC minimum bend radius of 7 inches and locate at approximately center vertical of the concrete slab The thermostat sensing bulb can later be pushed down this PVC conduit If the...

Page 5: ... Electro Boiler to the hydronics system The owner installer assumes all responsibility and or liability associated with any needed installation of the gas oil boiler pump plumbing system design hydronics systems or backup gas oil boiler etc Any instructions or comments made within this manual or factory phone assistance relating to the gas oil furnace are provided as comments of assistance and hel...

Page 6: ...d loop hydronic heating system an expansion tank is required Temperature Pressure Gauge Recommended to observe the operation of the system Actually a temperature gauge at the inlet and outlet is desirable Pressure Safety Valve This is required at the hot outlet and is furnished as a loose component with the boiler unit itself Failure to install the provided 30 PSI pressure relief valve as shown wi...

Page 7: ...TE This model series is designed and equipped for 240 volt residential single phase If this unit is used on 208 volt energy capacity is reduced by approximately 25 and there is a possibility of intermittent relay operation The installed transformer has a primary tap for 208 4 Circulating Pump the orange pigtail wires at the control board cube relay represent a switch closure see drawing 10 amp max...

Page 8: ...ify there is proper spacing between all power and electrical wire terminals and verify top high limit manual reset is in During shipping freight vibration there are times when the boiler vessel top manual reset high limit is popped out WATER ADDITIVES 1 Unless the source water is unusually poor and or rust elements additives are not required It is recommended the water source as shown on drawing B...

Page 9: ...nst the metal pipe and listen for air bubbles If the water flow is consistent and quiet the system is probably purged and water filled 9 Close the drain valve Open the inlet gate valve 10 The cold system pressure at the gauge should be approximately 1Ø to 14 PSI 11 Close water supply valve and disconnect water supply 12 Optional The circulating pump can be energized during this fill operation by h...

Page 10: ...angement This unit is factory setup in the W position meaning the pump will always run as a direct function of R to W operating thermostat By simply moving this black 2 position jumper to the L the pump will be turned off during load control interrupt 8 At outlet temperatures of approximately 160 F 53 C the maximum operating system pressure should be approximately 18 PSI 124 kPa If the PSI or kPa ...

Page 11: ...0 it should self reset and restart Manual reset limits surfaced mounted to the top of the vessel opens at 205 F This opens all 24V control power thus opening all element power relays The observed action is the same as a blown fuse no front panel boiler power LED To reset this device simply press the red button located on the limit switch Comment The hi limit auto reset LED and utility off peak LED...

Page 12: ......

Page 13: ......

Page 14: ......

Page 15: ......

Page 16: ......

Page 17: ......

Page 18: ...tem for Brand X boilers or dual EB R L E Series EB ZC 4 wiring and convenience interface isolated boiler end switch EB 5415A low cost 2 or 3 zones sheds one boiler stage Mini Boiler enhancement ZONE CONTROLLER SLAB STAT Sensing and controlling the system based upon radiant floor surface temperature or the concrete mass has very positive benefits Radiant floor air stat in the same area as a forced air...

Page 19: ...es boilers come standard equipped with outlet temperature pressure gauge pressure relief safety valve and when applicable the WarmFloTM electronic control sensors These kits provide the additional components for easy installation 5585 Mini Boiler 10 kW TS Series 5586 TS Series Standard 5578 3 4 Pipe 5582 1 Pipe 5579 1 1 4 Pipe 120V 1 25 HP maintenance free wet rotor circulator Pump curve example 5...

Page 20: ...ade by Electro Industries or its authorized representative Electro Industries will cover reasonable labor costs to repair defective product or product parts for ninety 90 days after installation TWENTY YEAR 20 LIMITED WARRANTY ON BOILER ELEMENTS AND VESSELS Electro Industries Inc warrants that the boiler elements and vessels of its products are free from defects in materials and workmanship throug...

Page 21: ...ill be null and void 4 The purchaser shall have maintained the product in accordance with the manual that accompanies the unit Annually a qualified and licensed contractor must inspect the product to assure it is in proper working condition 5 All related heating components must be maintained in good operating condition 6 All lines must be checked to confirm that all condensation drains properly fr...

Reviews: