2: Installation
Electro
Industries/GaugeTech
The Leader In Power Monitoring and Smart Grid Solutions
Electro
Industries/GaugeTech
The Leader In Power Monitoring and Smart Grid Solutions
2.2: Installation Step 2 - Drill the Wiring Holes
Cut the holes you need in the bottom of the enclosure for the power, CT, and
communications wiring. See the figure below for the allowable location.
Figure 2.2: Location for Punch Entries
The drawings show the area in the bottom of the enclosure where wiring holes can be
cut: 1” [25.40mm] from the front of the enclosure, 1.5” [38.10mm] from the right
side of the enclosure, 1.5” [38.10mm] from the back of the enclosure, and 3.75”
[95.25mm] from the left side of the enclosure.
PP
LQ
PP
LQ
3.75in
[95.25mm]
1.00in[25.40mm]
1.50in[38.10mm]
1.50in[38.10mm]
BOTTOM VIEW OF ENCLOSURE
WALL
You can cut holes
inside this area