19
5.7 PCS DC+ power and breaker assembly wiring
1.
Route the PCS DC+ power cable from the PCS
through the cabinet coupling port.
2.
Terminate the PCS DC+ cable,
referenced [P+], at the top right busbar
terminal of the DC breaker as shown. Torque
to 15 in/lbs.
3.
Terminate the DC+ power cables referenced B2
and B3 at the lower battery DC+ power posts as
shown. Mount only one cable per post
4.
Mount the breaker assembly to the cabinet wall
using the hardware provided.
Ref P/N
Description
Pylon p/n label
B2
#3796
DC+ breaker
cable RED 400
mm
WI0CUS300001
B3
#3797
DC+ breaker
cable RED 780
mm
WI0PUS300001
P+
#2923
PCS DC+ power
cable
-
1
2
3
4
Figure 16: Battery DC breaker wiring.