5.5 Wiring the battery modules
Follow the battery module power and communication
jumper wiring below.
5.5.1 Battery module DC -/+ jumper cable wiring
Install the cables in the following sequence as shown.
1.
Terminate the two DC- module jumper cables
referenced A1.
2.
Terminate the DC- module jumper cable
referenced A2.
3.
Terminate the two DC+ module jumper cables
referenced B1.
4.
Terminate the DC+ module jumper cable
referenced B2.
5.5.2 BMS communication jumper cable wiring
Install the cables in the following sequence.
IMPORTANT! All module interconnecting BMS
jumpers terminate at the [Linkport] terminals.
Note the Linkport reference, 0 an 1, for each port
connection.
1.
Terminate the BMS jumper cable C2 between
batteries #2 - 3.
2.
Terminate the BMS jumper cables C1 between
batteries #1-2 and #3-4.
Ref P/N
Description
Pylon p/n label
A1
#3790
DC- module
jumper BLK 180
mm
WI0BSC1000B2
A2
#3793
DC- module
jumper BLK 400
mm
WI0CUS300004
B1
#3789
DC+ module
jumper RED 180
mm
WI0BSC100001
B2
#3796
DC+ breaker
cable RED 400
mm
WI0CUS300001
C1
#3792
BMS jumper short
210 mm
WI0SRJ458025
C2
#3794
BMS jumper long
700 mm
WI0SUS300002
Figure 13: Battery module power wiring.