A541-11-880 Issue A
Page 24
© Edwards Limited 2010. All rights reserved.
Edwards and the Edwards logo are trademarks of Edwards Limited.
Installation
4. Inspect the water hoses, pipelines and connections and check that there are no leaks.
Turn off the water supply while you complete the remainder of the installation procedures.
3.12
Commission the iXL120 system
1. Switch on the external electrical supply and check that the power OK LED (
, item 4) is lit. If the LED is
not lit, contact Edwards.
2. Switch on the cooling-water supply.
3. Ensure that the exhaust-extraction system is not blocked (for example, that valves in the exhaust-extraction
system are open).
4. Ensure that all openings to atmospheric pressure in the foreline vacuum system are closed.
5. Press local control button (
, item 3). The green LED will illuminate. Then press the Start button
(
6. If the iXL120 system starts and continues to operate, continue at
. If a warning or alarm condition is
indicated:
Shut-down the iXL120 system: refer to
.
Contact Edwards.
7. After you have commissioned the iXL120 system:
If you want to continue to operate the iXL120 system, refer to
.
Otherwise, shut-down the system: refer to
WARNING
During some application cycles it is possible that the system may exceed OSHA 1910.95 Occupational
Noise Exposure Limits, the EU noise directive 2003/10/EC or other regional noise limits dependent
upon the process, duty cycle, installation or environment in which the system is being operated.
A sound pressure survey must be conducted after installation and, if necessary, controls
implemented to ensure that the relevant limits are not exceeded during operation and that
adequate precautions are taken to prevent personnel from exposure to high noise levels during
operation.