MOUNTING AND INSTALLATION OF PELLET BOILER BISOLID
5.1.
REQUIREMENTS FOR INSTALLATION OF PELLET BOILER BISOLID
When installing the hot water pellet boiler from series Bisolid is necessary to meet the
following basic requirements:
The room anticipated to install the boiler must provide a constant flow of fresh air
needed for combustion and good ventilation.
It is not allowed installation of the boiler in dwellings, including corridors.
Connecting the hot water pellet boiler from series Bisolid to the heating installation
must be performed only by authorized qualified technician.
Installation and maintenance of equipment with solid fuel is carried out by specialized
companies with the right to conduct such activities.
The hot water pellet boiler from series Bisolid is connected to the heating system with
CLOSED expansion vessel. In the event that the system is with closed expansion
vessel, in it must be installed pressure valve that opens when exceeding the
operating pressure of the boiler (0.25 MPa) and this valve must be certified in
accordance with PED 97/23.
Before the commissioning of the boiler there should be ensured complete filling with
water/liquid circulation and venting of the heating system.
Maintenance of the boiler should be performed only by adults who are familiar with
the instructions for use of the equipment.
The achieved heating output of the system: hot water pellet boiler from series Bisolid and
automated pellet burner with manually cleaning from series Bisolid GP xx_B hc> depends
on:
The heating output adjusted for the burner operation.
The contamination level of the boiler’s heat exchanging surfaces.
The sealing level of the door and combustion chamber’s covers (the sealing ropes
condition).
The chimney draught.
The efficiency coefficient of the system: hot water pellet boiler from series Bisolid and
automated pellet burner with manually cleaning from series Bisolid GP xx_B hc> in nominal
operation mode reaches 89% (depending on the specific system) – it can be achieved by
adjustment of the burner’s operation parameters by the use of gas-analyzer (to be performed
by an authorized servicing specialist).
5.2.
REQUIREMENTS FOR INSTALLATION OF PELLET BURNER BISOLID GP XX_B
HC> TO BOILER BISOLID
The automated pellet burner with manually cleaning from series Bisolid GP xx_B hc> has to
be mounted to the heat exchanger unit of the hot water pellet boiler from series Bisolid. The
boiler construction provides availability for “left” or “right” mounting of the burner, therefore
the suitable combination should be chosen during the preliminary system installation project.
During the mounting process a proper sealing between the modules/components must be
ensured in order to prevent intake of unorganized air from the environment or exhaust of flue
gasses. The following requirements must be also taken into account:
Easy access for cleaning of the burner’s fire-grate.
Secured safe operation conditions and maintenance of the system reliability.
Availability for adjustment and servicing of the system: heat exchanger of the pellet
boiler from series Bisolid (for example when necessary to clean it), burner from series
Bisolid GP xx_B hc> - for adjustment, necessity for maintenance and regulation,