![Ecotermal MODULE-T 10 kW Manual Download Page 9](http://html1.mh-extra.com/html/ecotermal/module-t-10-kw/module-t-10-kw_manual_2355595009.webp)
9
1.
Boiler should be mounted at a place suitable for servicing (free access thereto) and
possibility of opening the front lid.
2.
Boiler should be mounted suspended on the wall at minimum height of 1 m off the
floor.
3.
Water filter should be mounted at the cold water intake before the pump by observing
the direction marked on the filter itself (boiler fixture), in accordance with the
attached manufacturer’s instructions.
4.
The boiler should not be contaminated with building materials.
5.
Banjo fitting connections should be mounted on the boiler intake and the outlet.
6.
Hydraulic test should be carried out at an index of 1.25 above the operating pressure.
7.
Upon assembly, it is necessary the adjustments of the boiler and the blocking
thermostats to be checked up. The actual control is done during the warm test.
8.
The guarantee shall be effective as from the commissioning date, but not later than
six months as from the date of the purchase.