INSTALLATION, OPERATION AND MAINTENANCE MANUAL
20
Boiler room disposition layout
Fig. 22
illustrates minimum distances which must be kept in order to ensure safe operation of the boiler room and allow
manipulations with the boiler, such as cleaning and stoking. The distance between the front of the boiler and the wall should be at
least the boiler length L plus 500mm. Minimum distances between the boiler side and rear should be 800mm, with the distance of
the rear also determined by the way the boiler is connected to the chimney.
fig. 22
■
Do not touch hot water connections or the flue outlet when the boiler is operating.
Installation procedure
■
Place the boiler body on a non-flammable materials.
■
Install a thermal safety valve.
■
After connecting the boiler to the heating system, screw filling and drain stopcocks into the back section.
■
Screw the flue adapter with smoke flap onto the boiler combustion gases outlet.
■
Put a flue over the flue adapter and insert it into the chimney connection hole. The flue diameter is 150mm.
■
Install a thermo-mechanical output regulator into the opening in the top part of the front section.
■
We recommend fitting shutting valves on the hot water inlet and outlet, without which it would be necessary to drain the entire
heating system before the filter can be cleaned.
■
No shutting valve may be installed between the boiler and the expansion vessel.