§4.3.2 instrument well construction requirements
If need to install transducers in instrument well,there must be enough installation room,convenient
for people to stand up to work,distance between pipe wall and well wall is at least above
550mm,width is more than (D+550*2)mm,cement pipe width is more than
(D+700*2)mm,instrument well axial width L is more than D+1200mm.when installing
transducers,avoid the place of flange,welding line,reducing,do best to install transducers in the
range of +/-45° of horizontal position of pipe axis.
Attention:1,Do best to install transducers in the range of +/-45° of horizontal position of
pipe axis .
2,Connect the mainframe enclosure with ground.