Instruction Book    IB182312EN   June 2016   www.eaton.com

50/75/150 VCP-W

Selectable Ground and Test Device

g.   Repeat steps ‘f’ for the remaining selector blades of the SG&T 

terminals.

h.   Replace the removable barriers into their respective retainers 

before proceeding to the next step (Figure 5.3). 

i.    Close the terminal set door and secure it with the special 

Kirk™ lock bolt (if so equipped.) The Kirk™ Lock bolt is pushed 

through the door hasp and into the Kirk™ lock itself. Turn the 

Kirk™ key to retain the special bolt and release the Kirk™ key 

from the lock cylinder. (Figure 5.1).

j.    If the other set of terminals are to be accessed and grounded, 

start at ‘a’ above to ground the other set of terminals, if the 

SG&T is the six terminal type.

k.   When all tests are complete, return the selector blades to the 

neutral position and re-install the removable barriers. 

l.    The SG&T may now be removed from the switchgear circuit 

breaker compartment using the removal procedure in Section 

5.5.

 DANGER

FAILURE TO RETURN THE SELECTABLE BLADES TO THE NEUTRAL 

POSITION INSIDE THE SG&T AFTER TESTING IS COMPLETE WILL CAUSE 

DEATH, SERIOUS INJURY, AND/OR PROPERTY DAMAGE. A THREE 

PHASE BOLTED FAULT WILL OCCUR IF THE CIRCUIT IS INADVERTENTLY 

ENERGIZED. 

5.5 INSERTION PROCEDURE

 CAUTION

THE MAIN SWITCHGEAR BUS AND SWITCHGEAR LOAD CONNECTIONS 

ARE CONNECTED WHEN THIS GROUND AND TEST DEVICE IS RACKED TO 

THE ‘CONNECTED’ POSITION. ALL PRIMARY CIRCUITS MUST BE FULLY 

DE-ENERGIZED, LOCKED AND TAGGED OUT TO PREVENT INADVERTENT 

ENERGIZATION. CONFIRM THAT LINE AND LOAD PRIMARY CIRCUITS 

ARE NOT BACKFED THROUGH SECONDARY CONTROL CIRCUITS SUCH AS 

POTENTIAL TRANSFORMERS OR CONTROL POWER TRANSFORMERS. THIS 

GROUND AND TEST DEVICE MUST BE OPERATED ONLY WITH A WELL 

MAINTAINED AND CERTIFIED ‘HOT STICK’.

 DANGER

FAILURE TO REMOVE ALL SOURCES OF POWER FROM THE CIRCUIT 

BREAKER COMPARTMENT BEING GROUNDED WILL RESULT IN PERSONAL 

INJURY AND PROPERTY DAMAGE. APPROPRIATE PERSONAL PROTECTIVE 

EQUIPMENT (PPE) MUST BE IN PLACE PRIOR TO OPERATING THIS SG&T.

 WARNING

EXAMINE THE INSIDE OF THE CELL BEFORE INSERTING THE SG&T FOR 

EXCESSIVE DIRT OR ANYTHING THAT MIGHT INTERFERE WITH THE SG&T 

TRAVEL.

KEEP HANDS OFF THE TOP EDGE OF THE FRONT BARRIER WHEN PUSHING 

A SG&T INTO A CELL. FAILURE TO DO SO COULD RESULT IN BODILY 

INJURY, IF FINGERS BECOME WEDGED BETWEEN THE SG&T AND THE 

CELL. USE BOTH FULLY OPENED HANDS FLAT ON THE FRONT OF THE SG&T 

TO ADVANCE INTO THE STRUCTURE.

If the VCP-W SG&T is being inserted into an upper compartment 

or will be positioned in a lower compartment without the use of a 

drawout ramp or dockable dolly, the extension rails must first be 

put in position. Carefully engage the left and right extension rails to 

the fixed structure rails and ensure they are properly seated in place 

(Figure 5.9). Once the extension rails are properly in place, the SG&T 

can be carefully loaded on the extension rails using an overhead lifter 

and lifting yoke. Remove the lifting yoke when the SG&T is securely 

seated on the extension rails.

Figure 5.9. Inserting Guide Rails

Figure 5.10. Racking the SG&T Device

Push the SG&T into the compartment until the Disconnect/Test 

position is reached as confirmed by a metallic sound of the racking 

latch engaging the racking nut (Figures 5.10). Once the SG&T is in 

the Disconnect/Test position, the extension rails can be removed.

 WARNING

DO NOT USE ANY TOOL OTHER THAN THE RACKING-IN CRANK PROVIDED 

TO LEVER THE SG&T FROM TEST OR CONNECTED POSITIONS. CORRECT 

OPERATION OF SOME OF THE INTERLOCKS IS DEPENDENT ON USE OF THE 

PROVIDED RACKING CRANK. PERSONAL INJURY OR EQUIPMENT DAMAGE 

COULD RESULT FROM THE USE A TOOL OTHER THAN THE PROPER 

RACKING-IN CRANK.

To move the VCP-W SG&T to the CONNECTED position, engage 

the racking-in crank with the structure mounted racking shaft 

(Figure 5.10). Turn the racking-in crank in a clockwise direction and 

the SG&T will move slowly toward the rear of the structure. When 

the SG&T reaches the CONNECTED position (Figure 5.11), it will 

become impossible to continue turning the racking-in crank. The 

CONNECTED position will also be indicated by a red flag indicator 

just below the racking device. 

5.5  REMOVAL PROCEDURE 

To remove the SG&T device from the CONNECTED position, engage 

the racking handle onto the circuit breaker compartment mounted 

racking shaft. Turn the racking handle counterclockwise until the 

SG&T reaches the ‘disconnect/test’ position. When the ‘disconnect/

test’ position is reached, it will not be possible to turn the racking 

handle any further. The ‘disconnect/test’ position is indicated by a 

green indicator below the racking device.

Summary of Contents for VCP-W Series

Page 1: ...Instruction Book IB182312EN 50 75 150 VCP W Selectable Ground and Test Device 150 VCP W SGT June 2016 Supersedes October 2015 Effective...

Page 2: ...an Eaton sales office should be consulted Sale of the product shown in this literature is subject to the terms and conditions outlined in appropriate Eaton selling policies or other contractual agree...

Page 3: ...4 2 BUSHINGS AND DISCONNECTING CONTACT ASSEMBLIES 11 4 3 GROUNDING CONTACTS 11 4 4 BREAKER CELL CODING PLATES 11 4 5 CELL POSITION DESCRIPTION 11 4 6 DEVICE AMPERAGE CONVERSION PROCEDURE 13 SECTION 5...

Page 4: ...N AND VAST VARIETY OF SYSTEM USER REQUIREMENTS SPECIFIC SAFE OPERATING PROCEDURES FOR THE USE OF THIS DEVICE MUST BE DEVELOPED BY THE USER WARNING SATISFACTORY PERFORMANCE OF SELECTABLE GROUND AND TES...

Page 5: ...able Ground and Test Device Dimensions Breaker Type Sized For Circuit Breaker Compartment Amps A B C D E F G H I J K 150 VCP W 500 Dual 1200 2000 28 50 26 76 10 00 27 81 12 00 14 13 20 88 24 63 2 25 2...

Page 6: ...n the device Failure to do so could result in electrical shock leading to death severe personnel injury or property damage Do not leave the selectable ground and test device in an intermediate positio...

Page 7: ...Services System office Tools and Accessories Racking Handle The racking handle is used to drive the racking mechanism which moves the SG T device into and out of the cell This racking handle is the s...

Page 8: ...g objects excessive moisture etc must be provided Container should be arranged to permit free circulation of air on all sides and temporary heaters should be used to minimize condensation Moisture can...

Page 9: ...ront External View of 150 VCP W SG T Device 3 2 1 8 5 4 7 6 Front External View 150 VCP W SG T Shown 1 Lock out Tag out Ring 4 KirkTM Key Interlock 7 Lift Pull Handle 2 Friction Hinge 5 Spring Loaded...

Page 10: ...une 2016 www eaton com 50 75 150 VCP W Selectable Ground and Test Device Figure 3 3 b Rear External View of 150 VCP W SG T Device Back External View 150 VCP W SG T Shown 1 Lifting Point 2 Primary Disc...

Page 11: ...als in the switchgear compartment Figure 3 5 4 3 GROUNDING CONTACTS The grounding contact is an assembly of spring loaded fingers which ground the device by engaging the switchgear cell grounding bus...

Page 12: ...4 5 Primary Disconnect Shim Removal 3000A Figure 4 8 Primary Disconnect Installed 1200A 2000A Figure 4 6 Primary Disconnect Installation 1200A 2000A Figure 4 4 Primary Disconnect Removal 3000A Figure...

Page 13: ...roperly stored to avoid potential damage Figure 4 4 Note N Ensure shims are installed as shown in Figure 4 5 for the 3000A configuration c THE GROUND AND TEST CODE PLATE MUST BE CHANGED AT THIS TIME T...

Page 14: ...IN THE NEUTRAL POSITION b For SG T devices equipped with Kirk Locks on the terminal access doors use the Kirk key provided to release the special bolt that is held by the Kirk locking system Slide th...

Page 15: ...5 3 Selector Blade Figure 5 6 Utilizing Hot Stick To Engage Selector Blade Figure 5 5 Selector Blade Disengaged Shown in Upper Position Figure 5 7 Selector Blade Engaged Shown in Upper Position Figure...

Page 16: ...IER WHEN PUSHING A SG T INTO A CELL FAILURE TO DO SO COULD RESULT IN BODILY INJURY IF FINGERS BECOME WEDGED BETWEEN THE SG T AND THE CELL USE BOTH FULLY OPENED HANDS FLAT ON THE FRONT OF THE SG T TO A...

Page 17: ...e In Connect Position Figure 5 12 Removing SG T using Lift Pull Handle To remove the SG T from the cell install the extension guide rails Pull up on the Lift Pull Handle as shown in Figure 5 12 then p...

Page 18: ...uired to cut dirt used Stoddard s Solvent Eaton part number 55812CA or commercial equivalent Hardware Visually inspect all hardware Replace any damaged or missing hardware with parts equivalent to tho...

Page 19: ...ating experience 7 1 1 ORDERING INSTRUCTIONS 1 Always specify the selectable ground and test device rating information and general order number from the nameplate 2 Describe the item give the style nu...

Page 20: ...ulevard Cleveland OH 44122 United States Eaton com 2016 Eaton All Rights Reserved Printed in USA Publication No IB182312EN June 2016 Eaton is a registered trademark All trademarks are property of thei...

Reviews: