UPS SYSTEM INSTALLATION
Eaton 9395 UPS (450–825 kVA) Installation and Operation Manual
S
164201725 Rev 4
www.eaton.com/powerquality
4-3
Shipping Bracket
Bolts
Shipping Bracket
Bolts
Pallet
Right Side Shipping
Bracket
ISBM Removable
Front Panels
Figure 4‐2. Removing the ISBM Section Right Side Shipping Bracket
4.
Using a forklift (see the caution statement at the beginning of this procedure),
raise the cabinet until the cabinet bottom clears the pallet by approximately
3 mm (1/8
”
).
5.
Pull the pallet from under the cabinet. Discard or recycle the pallet and shipping
brackets in a responsible manner.
6.
Carefully lower the cabinet until the cabinet base contacts the floor.
7.
Repeat Steps 2 through 6 for the remaining cabinet.
8.
Proceed to paragraph 4.3.