Powerware 9125 (2500–3000 VA) Seismic Kit
7
Powerware
®
9125 (2500–3000 VA) Seismic Kit Installation Instructions
S
Rev A
www.powerware.com
3.
On the back of each cabinet, remove the screw on the top left
corner and discard (see Figure 6).
Figure 6. Removing Cabinet Screws
4.
Beginning with a middle position, slide each cabinet into place.
NOTE
The PDM must be installed to the left of the UPS and the EBM(s)
must be installed to the right of the UPS.
Figure 7. Sliding in a Cabinet