EATON
Powerware
®
225 kVA PDU Installation and Operation Manual
S
164201629 Rev D
www.powerware.com
6−1
Chapter 6
PDU Operating Instructions
This section describes how to operate the PDU.
NOTE
Before starting the PDU, ensure all installation tasks are complete and a preliminary startup has
been performed by an Eaton Customer Service Engineer. The preliminary startup verifies all electrical
interconnections to ensure the installation was successful and the PDU operates properly.
NOTE
Read this section of the manual and have thorough knowledge of PDU operation before attempting
to operate any of the controls.
6.1
PDU Controls and Displays
Figure 6-1 through Figure 6-4 identify and show the location of the controls on the
PDU and optional sidecars. The descriptions provide a brief overview of the PDU
controls with standard and optional features.
NOTE
Read the operation sections of this manual and have thorough knowledge of PDU operation before
attempting to operate any of the PDU controls.
The PDU can contain the following controls and displays:
S
Main input breaker CB1
S
TVSS status display
S
Emergency Power−off (EPO)
S
Control panel
S
PDU right and left distribution panels with panel input breakers
S
Four left and four right PDU subfeed breakers
S
Sidecar top and bottom distribution panels with panel input breakers
Figure 6Table 6
Summary of Contents for Powerware 225 kVA Three-Phase Power Distribution...
Page 141: ......
Page 142: ...164201629D 164201629 D...